1021 S KINGSLEY DR 90006
Certificate Information: 1021 S KINGSLEY DR 90006
- Application / Permit
- 19016-10000-30452
- Plan Check / Job No.
- B19LA20262
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL PLYWOOD SHEARWALL.
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Metro
- Current Status
- Issued on 1/19/2024
Permit Application Status History
| Submitted | 9/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2019 | MANUEL MONTUFAR |
| Corrections Issued | 10/21/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 10/21/2019 | SAI KHUM |
| Building Plans Picked Up | 10/24/2019 | APPLICANT |
| Plan Check Approved | 12/17/2019 | MANUEL MONTUFAR |
| Issued | 1/19/2024 | APPLICANT |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 12/11/2019 | GRACIELA ACOSTA |
| Housing rent stabilization | Cleared | 2/6/2020 | CHARLES GARCIA |
Contact Information
| Contractor | 1 Design Construction Corp; Lic. No.: 929941-B | 2511 BEVERLY BLVD LOS ANGELES, CA 90057 |
| Engineer | Lee,, Sang Wook; Lic. No.: C56699 | 4943 ROSEWOOD AVE 202 LOS ANGELES, CA 90004 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/26/2024 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 1/29/2024 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 1/30/2024 | Conditional Approval | JACOB MYERS |
| Deputy Wood Construction | 2/13/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 2/14/2024 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 2/20/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 2/27/2024 | Partial Approval | JACOB MYERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 3/7/2024 | Approved | DARRYL ARNOLD |
| Final | 3/29/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 3/29/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 5/3/2024 | Partial Inspection | JACOB MYERS |
| Smoke Detectors | 5/3/2024 | Not Ready for Inspection | JACOB MYERS |