3626 S 11TH AVE 90018
Certificate Information: 3626 S 11TH AVE 90018
- Application / Permit
- 19016-10000-30408
- Plan Check / Job No.
- B19LA20240
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CORE AND SHELL RENOVATION IN EXISTING OFFICE BUILDING, NEW ROOFING MATERIAL AND MORE OPENINGS ON THE SOUTH WITH NEW PARTITION INSIDE, RECONFIGURE ADA PARKINGS. 1 OF 2
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/5/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | JOHNNY WU |
| Corrections Issued | 10/15/2019 | JOHNNY WU |
| Quality Review Completed | 10/31/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/4/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 11/5/2019 | APPLICANT |
| Green Plans Picked Up | 11/5/2019 | APPLICANT |
| Applicant returned to address corrections | 12/5/2019 | JOHNNY WU |
| Applicant returned to address corrections | 12/17/2019 | JOHNNY WU |
| Plan Check Approved | 12/19/2019 | JOHNNY WU |
| Issued | 2/5/2020 | LADBS |
| TCO Issued (Expire Date: 06-02-2021) | 12/4/2020 | DAVID TSAU |
| TCO Issued (Expire Date: 11-16-2021) | 5/20/2021 | DAVID TSAU |
Permit Application Clearance Information
| Permit | Cleared | 12/4/2019 | ELAINE LEI |
| Prkng lot landscape/Water mgmt | Cleared | 12/4/2019 | TERRI OSBORNE |
| Tract Map conditions | Cleared | 12/4/2019 | TERRI OSBORNE |
| ZA Case | Cleared | 12/4/2019 | TERRI OSBORNE |
| ZA Case | Cleared | 12/4/2019 | TERRI OSBORNE |
| Specific Plan | Cleared | 12/5/2019 | JASON CHAN |
| ZI | Cleared | 12/5/2019 | JASON CHAN |
| DAS Clearance | Cleared | 12/11/2019 | SHINE LIN |
| Green Code | Cleared | 12/12/2019 | VIVIAN LAO |
Contact Information
| Architect | Swartz,, David Louis; Lic. No.: C19729 | 1437 4TH STREET SUITE 400 SANTA MONICA, CA 90401 |
| Contractor | Build Solutions; Lic. No.: 1047137-B | 2226 PATRICIA AVENUE LOS ANGELES, CA 90064 |
| Engineer | Breaks,, Matthew Calvin; Lic. No.: S6028 | 5056 TUJUNGA AVE APT 17 NORTH HOLLYWOOD, CA 91601 |
| Engineer | Risha,, Janah Adib; Lic. No.: C46811 | 410 EAST CYPRESS AVE BURBANK, CA 91501 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 2/24/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 2/28/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 2/28/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 2/28/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 3/2/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Wood Construction | 3/4/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2020 | Partial Inspection | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 3/5/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 3/6/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 3/11/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 3/12/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 3/13/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 3/16/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 3/31/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 4/8/2020 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 4/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 4/30/2020 | Approved | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 4/30/2020 | Approved | LEOPOLDO MENDOZA |
| Drywall Nailing | 5/4/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Final | 6/19/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| Green Building Final | 6/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Rough | 6/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| METHANE-Final | 6/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| METHANE-Rough | 6/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Reinforced Masonry Frame | 6/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 6/19/2020 | SGSOV No Gas | LEOPOLDO MENDOZA |
| Smoke Detectors | 6/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 7/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 7/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Rough | 7/2/2020 | Approved | LEOPOLDO MENDOZA |
| METHANE-Final | 7/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| METHANE-Rough | 7/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Reinforced Masonry Frame | 7/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Smoke Detectors | 7/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 8/7/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 8/7/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Insulation | 8/7/2020 | Approved | LEOPOLDO MENDOZA |
| METHANE-Final | 8/7/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| METHANE-Rough | 8/7/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Reinforced Masonry Frame | 8/7/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Smoke Detectors | 8/7/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 8/14/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 8/20/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 8/21/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Final | 9/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 9/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| METHANE-Final | 9/15/2020 | Approved | LEOPOLDO MENDOZA |
| METHANE-Rough | 9/15/2020 | Approved | LEOPOLDO MENDOZA |
| Reinforced Masonry Frame | 9/15/2020 | Approved | LEOPOLDO MENDOZA |
| Smoke Detectors | 9/15/2020 | Approved | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 9/17/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 10/9/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 10/9/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 10/14/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 10/27/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 10/28/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 10/28/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Deputy Reinf. Masonry | 10/29/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 11/4/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 11/4/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 11/6/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 11/6/2020 | Approved | LEOPOLDO MENDOZA |
| Final | 11/18/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 12/2/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Special/Order Compliance | 5/5/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Special/Order Compliance | 10/20/2021 | Partial Inspection | RUSSELL BONVOULOIR |