15223 W BURBANK BLVD 91411

Certificate Information: 15223 W BURBANK BLVD 91411

Application / Permit
19016-10000-30382
Plan Check / Job No.
B19LA20219
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
CHANGE OF USE FROM SCHOOL/ OFFICE TO RETAIL/STORAGE. INTERIOR ALTERATIONS. NEW METAL CANOPY. INSTALL (2) NEW 2-CAR CARLIFTS
Permit Issued
Issued on 6/30/2020
Issuing Office
Current Status
CofO Issued on 3/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 VU NGUYEN
Disabled Access Plans Picked Up 10/4/2019 APPLICANT
Green Plans Picked Up 10/11/2019 APPLICANT
Corrections Issued 10/15/2019 VU NGUYEN
Quality Review Completed 10/30/2019 JOSE RODRIGUEZ
Building Plans Picked Up 11/1/2019 APPLICANT
Applicant returned to address corrections 1/2/2020 VU NGUYEN
Applicant returned to address corrections 2/4/2020 VU NGUYEN
Applicant returned to address corrections 2/18/2020 VU NGUYEN
Plan Check Approved 6/30/2020 VU NGUYEN
Issued 6/30/2020 APPLICANT
CofO in Progress 3/16/2021 ANDREW DORSO
CofO Issued 3/19/2021 JEFFREY DURAN
Permit Finaled 3/19/2021 JEFFREY DURAN

Permit Application Clearance Information

CPC Cleared 12/6/2019 TERRI OSBORNE
Supp. Use District POD/CDO/TDO Cleared 12/6/2019 TERRI OSBORNE
ZA Case Cleared 12/6/2019 TERRI OSBORNE
DAS Clearance Cleared 12/19/2019 SHINE LIN
Green Code Cleared 12/24/2019 KHEDER ALRAZAA

Contact Information

Architect Banuelos,, Timothy J; Lic. No.: C27086 2325 ESTRELLA COURT      PINOLE, CA 94564
Contractor Alta Construction Incorporated; Lic. No.: 890027-B 369 E BLAINE STREET      CORONA, CA 92879
Engineer Sierra,, Jesus Francisco; Lic. No.: S3298 39812 MISSION BOULEVARD SUITE 100      FREMONT, CA 94539

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2020 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 8/4/2020 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 8/5/2020 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Corrections Issued ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 8/6/2020 Partial Approval DANIEL VARNUM
Insulation 8/12/2020 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 8/12/2020 Partial Inspection ANDREW DORSO
Deputy Wood Construction 8/13/2020 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Approved ANDREW DORSO
Special/Order Compliance 8/13/2020 Approved JEFFREY DURAN
Green Building Rough 8/14/2020 Approved ANDREW DORSO
Wood Frame 8/14/2020 Approved ANDREW DORSO
Insulation 8/17/2020 Partial Inspection ANDREW DORSO
Interior/Exterior Lathing 8/19/2020 Approved ANDREW DORSO
Insulation 8/21/2020 Approved DANIEL VARNUM
Drywall Nailing 8/24/2020 Approved DANIEL VARNUM
Special/Order Compliance 12/9/2020 Partial Inspection DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 1/19/2021 Approved ROBERT DAVIS
Final 3/3/2021 Not Ready for Inspection ANDREW DORSO
Green Building Final 3/3/2021 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 3/3/2021 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 3/3/2021 Not Ready for Inspection ANDREW DORSO
Final 3/12/2021 OK to Issue CofO ANDREW DORSO
Green Building Final 3/12/2021 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved ANDREW DORSO
Smoke Detectors 3/12/2021 Approved ANDREW DORSO