1629 S VETERAN AVE 90024
Certificate Information: 1629 S VETERAN AVE 90024
- Application / Permit
- 19016-10000-30138
- Plan Check / Job No.
- B19LA20054
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- MAJOR REMODEL TO (E) 3-STORY APARTMENT BUILDING OVER GARAGE PARKING: INTERIOR & EXTERIOR CHANGES, NEW BEDROOMS, REMODELED KITCHENS/BATHROOMS, RESTRIPING OF EXISTING PARKING.
- Permit Issued
- Issued on 5/19/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 9/30/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 10/10/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 10/16/2019 | APPLICANT |
| Applicant returned to address corrections | 12/31/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 2/25/2020 | EMMANUEL MARTINEZ |
| Green Plans Picked Up | 5/6/2020 | APPLICANT |
| Issued | 5/19/2020 | LADBS |
| CofO in Progress | 6/8/2023 | GRANT WOODS |
| Permit Finaled | 6/9/2023 | DAVID TSAU |
| CofO Issued | 6/9/2023 | DAVID TSAU |
| Permit Finaled | 6/9/2023 | DAVID TSAU |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/7/2020 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 2/7/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/7/2020 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 2/7/2020 | HERMINIGILDO AGUSTIN |
| Abandoned oil well approval | Cleared | 2/12/2020 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 2/12/2020 | JOHN CONNEALLY |
| "Q" conditions | Cleared | 2/13/2020 | JULIA DUNCAN |
| Specific Plan | Cleared | 2/13/2020 | JULIA DUNCAN |
| Specific Plan | Cleared | 2/13/2020 | JULIA DUNCAN |
| ZA Case | Cleared | 2/13/2020 | RICHARD REASER |
| Green Code | Cleared | 2/19/2020 | VIVIAN LAO |
| DAS Clearance | Cleared | 2/20/2020 | EMMANUEL MARTINEZ |
| Fire Marshall Fire Life Safety | Cleared | 2/24/2020 | WILLIAM JOHNS |
Contact Information
| Contractor | M A S Construction Group Inc; Lic. No.: 1014814-B | 1543 7TH STREET SUITE 100 SANTA MONICA, CA 90401 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 1386 EAST WALNUT STREET SUITE 202 PASADENA, CA 91106 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2020 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 8/31/2020 | Conditional Approval | PAUL DAVIDSON |
| Pre-Inspection | 9/8/2020 | Approved | PAUL DAVIDSON |
| Pre-Inspection | 9/16/2020 | Partial Approval | PAUL DAVIDSON |
| Special/Order Compliance | 10/29/2020 | Partial Inspection | PAUL DAVIDSON |
| Special/Order Compliance | 1/4/2021 | Partial Inspection | PAUL DAVIDSON |
| Special/Order Compliance | 3/12/2021 | Corrections Issued | PAUL DAVIDSON |
| Pre-Inspection | 4/15/2021 | Partial Approval | PAUL DAVIDSON |
| Structural Steel Frame | 5/14/2021 | Partial Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 6/17/2021 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 6/29/2021 | Partial Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/6/2021 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 7/20/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 7/26/2021 | Partial Inspection | PAUL DAVIDSON |
| Wall Anchors | 8/3/2021 | Approved | PAUL DAVIDSON |
| Wood Frame | 8/3/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 8/4/2021 | Approved | PAUL DAVIDSON |
| Footing/Foundation/Slab | 8/12/2021 | Partial Approval | DERRICK SPENCER |
| Insulation | 8/12/2021 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2021 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 8/23/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 9/1/2021 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 9/1/2021 | Corrections Issued | PAUL DAVIDSON |
| Pre-Inspection | 9/10/2021 | Partial Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 9/16/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Insulation | 9/21/2021 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 9/21/2021 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 9/21/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 9/29/2021 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 9/29/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 10/4/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 10/12/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 10/18/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 12/1/2021 | Partial Approval | PAUL DAVIDSON |
| Insulation | 12/20/2021 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 12/22/2021 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 12/28/2021 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 1/4/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 2/8/2022 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 2/18/2022 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 3/1/2022 | Partial Inspection | GRANT WOODS |
| Light Gage Steel Frame | 3/9/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 3/24/2022 | Approved | JOHN DODGE |
| T-Bar Ceiling | 3/24/2022 | Approved | JOHN DODGE |
| Drywall Nailing | 3/31/2022 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 8/12/2022 | Partial Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 10/4/2022 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 10/19/2022 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 4/25/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Pre-Inspection | 4/27/2023 | Approved | PAUL DAVIDSON |
| Final | 5/10/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 5/10/2023 | Approved | PAUL DAVIDSON |
| METHANE-Final | 5/10/2023 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 5/10/2023 | Approved | PAUL DAVIDSON |
| Final | 6/2/2023 | Conditional Approval | PAUL DAVIDSON |
| Final | 6/6/2023 | Conditional Approval | GRANT WOODS |
| Final | 6/7/2023 | Conditional Approval | GRANT WOODS |