4441 1/2 S AVALON BLVD 90011
Certificate Information: 4441 1/2 S AVALON BLVD 90011
- Application / Permit
- 19016-10000-30122
- Plan Check / Job No.
- B19LA20038
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) SINGLE FAMILY DWELLING. REPLACE CEILING JOISTS, ADD NEW DRYWALL THROUGHOUT, REMODEL BATHROOM, REPLACE EXISTING ROOF NEW CLASS A ROOF, STUCCO PATCH.
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/8/2021
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2019 | KEVIN MORALES |
| Corrections Issued | 9/20/2019 | KEVIN MORALES |
| Plan Check Approved | 1/29/2020 | SHANGQIN XIE |
| Issued | 1/29/2020 | LADBS |
| Permit Finaled | 4/8/2021 | ROBERT MCDOWELL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 10/3/2019 | ANNA VIDAL |
| Project located in CRA area | Cleared | 10/3/2019 | JIM URQUHART |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/31/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 1/31/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/31/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 1/31/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 3/26/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/25/2020 | No Access for Inspection | FREDDIE RIVERA |
| Insulation | 10/5/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 2/4/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/4/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 2/5/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 2/5/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/8/2021 | Permit Finaled | ROBERT MCDOWELL |
| Gas Test | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Green Building Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 4/8/2021 | Approved | ROBERT MCDOWELL |