5540 N BONNER AVE 91601
Certificate Information: 5540 N BONNER AVE 91601
- Application / Permit
- 19016-10000-30073
- Plan Check / Job No.
- B19LA20012
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV.93 INSTALLING (1) SMF
- Permit Issued
- Issued on 7/13/2020
- Issuing Office
- Current Status
- Issued on 7/13/2020
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | GARO TELMI |
| Corrections Issued | 11/13/2019 | GARO TELMI |
| Quality Review Completed | 11/13/2019 | KEN GILL |
| Building Plans Picked Up | 11/19/2019 | APPLICANT |
| Plan Check Approved | 1/8/2020 | GARO TELMI |
| Issued | 7/13/2020 | APPLICANT |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/8/2020 | PHILLIP MUNGUIA |
| Historic Resource Verification | Cleared | 6/29/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 7/10/2020 | DAVID URITA |
Contact Information
| Contractor | Ces4 Construction; Lic. No.: 1042127-B | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 8/20/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/27/2020 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 8/27/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/1/2020 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/10/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 9/15/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/15/2020 | Approved | JOE VELASQUEZ |
| Final | 10/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/1/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 10/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 4/20/2023 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/20/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/20/2023 | Approved | DARRYL ARNOLD |
| Special/Order Compliance | 11/20/2023 | Approved | DARRYL ARNOLD |