432 S COLYTON ST 90013

Certificate Information: 432 S COLYTON ST 90013

Application / Permit
19016-10000-30032
Plan Check / Job No.
B19LA19970
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
PROPOSED CHANGE OF USE FROM WAREHOUSE TO OFFICE.
Permit Issued
Issued on 12/6/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 MICHAEL LOPEZ
Corrections Issued 10/2/2019 MICHAEL LOPEZ
Disabled Access Plans Picked Up 10/4/2019 APPLICANT
Quality Review Completed 10/5/2019 STANLEY RAAP
Building Plans Picked Up 10/11/2019 APPLICANT
Applicant returned to address corrections 11/7/2019 MICHAEL LOPEZ
Plan Check Approved 11/19/2019 MICHAEL LOPEZ
Issued 12/6/2019 LADBS
CofO in Progress 11/18/2020 RONALD PACHECO
CofO Issued 11/24/2020 DAVID TSAU
Permit Finaled 11/24/2020 DAVID TSAU

Permit Application Clearance Information

ZI Cleared 11/4/2019 ANNA VAN
DAS Clearance Cleared 11/7/2019 CHOI YAN
Eng Process Fee Ord 176,300 Cleared 11/19/2019 EMIL KYUPELYAN
Sewer availability Cleared 11/19/2019 EMIL KYUPELYAN

Contact Information

Architect , ; Lic. No.: C36846       ,
Contractor Laughton Trenton; Lic. No.: 1045667-B 1906 N BEVERLY GLEN BLVD      LOS ANGELES, CA 90077
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2019 Partial Inspection JEFFREY FULTON
Pre-Inspection 12/9/2019 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/11/2019 Conditional Approval JEFFREY FULTON
Wood Frame 12/13/2019 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/19/2019 Partial Inspection JEFFREY FULTON
Wood Frame 12/19/2019 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/20/2019 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/24/2019 Partial Inspection ERNESTO CORRAL
Final 1/10/2020 Not Ready for Inspection ERNESTO CORRAL
METHANE-Final 1/10/2020 Not Ready for Inspection ERNESTO CORRAL
METHANE-Rough 1/10/2020 No Access for Inspection ERNESTO CORRAL
Reinforced Masonry Frame 1/10/2020 No Access for Inspection ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 1/10/2020 SGSOV Not Ready ERNESTO CORRAL
Smoke Detectors 1/10/2020 Not Ready for Inspection ERNESTO CORRAL
Wood Frame 2/6/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 2/12/2020 Not Ready for Inspection JONATHAN QUACH
Insulation 2/14/2020 Conditional Approval LANNY MERRICK
Drywall Nailing 2/24/2020 Partial Approval JONATHAN QUACH
Interior/Exterior Lathing 2/28/2020 Partial Approval JONATHAN QUACH
Interior/Exterior Lathing 3/2/2020 Approved LANNY MERRICK
Special/Order Compliance 5/22/2020 Partial Inspection RONALD PACHECO
Final 7/9/2020 Corrections Issued RONALD PACHECO
METHANE-Final 7/9/2020 Not Ready for Inspection RONALD PACHECO
METHANE-Rough 7/9/2020 Not Ready for Inspection RONALD PACHECO
Reinforced Masonry Frame 7/9/2020 Not Ready for Inspection RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 7/9/2020 SGSOV Not Ready RONALD PACHECO
Smoke Detectors 7/9/2020 Not Ready for Inspection RONALD PACHECO
Special/Order Compliance 7/10/2020 Not Ready for Inspection RONALD PACHECO
Deputy Steel/Welding 8/4/2020 Conditional Approval LANNY MERRICK
Final 10/14/2020 Not Ready for Inspection RONALD PACHECO
METHANE-Final 10/14/2020 Approved RONALD PACHECO
METHANE-Rough 10/14/2020 Approved RONALD PACHECO
Reinforced Masonry Frame 10/14/2020 Approved RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Approved RONALD PACHECO
Smoke Detectors 10/14/2020 Approved RONALD PACHECO
Special/Order Compliance 10/15/2020 Conditional Approval RONALD PACHECO
Final 11/10/2020 Conditional Approval RONALD PACHECO