1718 S BUNDY DR 90025

Certificate Information: 1718 S BUNDY DR 90025

Application / Permit
19016-10000-29910
Plan Check / Job No.
B19LA19888
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LAMC DIV 93. INSTALL SSW.
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofC Issued on 9/6/2022

Permit Application Status History

Submitted 9/19/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 VARAND SARKISIAN
Corrections Issued 11/5/2019 VARAND SARKISIAN
Re-Submittal Required 11/13/2019 SAI KHUM
Building Plans Picked Up 1/10/2020 APPLICANT
Re-Submitted 10/19/2020 VARAND SARKISIAN
Corrections Issued 2 10/19/2020 VARAND SARKISIAN
Submitted for Second Quality Review 10/19/2020 VARAND SARKISIAN
Quality Review Completed 10/22/2020 DAVID CHANG
Plan Check Approved 10/27/2020 VARAND SARKISIAN
Issued 9/8/2021 APPLICANT
OK for CofC 9/2/2022 GRANT WOODS
CofC Issued 9/6/2022 DAVID TSAU

Permit Application Clearance Information

Tenant Habitability Plan Cleared 9/7/2021 RICHARD BRINSON

Contact Information

Contractor A List Builders Inc; Lic. No.: 952112-B 13237 CHANDLER BLVD      SHERMAN OAKS, CA 91401
Engineer Daniel, E Mcauliffe Jr.; Lic. No.: C89187       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/30/2021 Not Ready for Inspection JOHN DODGE
Footing/Foundation/Slab 9/30/2021 Approved JOHN DODGE
Deputy Reinf. Concrete 10/5/2021 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 10/5/2021 Approved JOEY BUCHANAN
Footing/Foundation/Slab 10/5/2021 Approved JOEY BUCHANAN
Wood Frame 10/13/2021 Approved ALAN NOVAK
Drywall Nailing 10/29/2021 Not Ready for Inspection ALAN NOVAK
Interior/Exterior Lathing 10/29/2021 Not Ready for Inspection ALAN NOVAK
Final 7/14/2022 Not Ready for Inspection ALAN NOVAK
SGSOV-Seismic Gas S/O Valve 7/14/2022 SGSOV Not Ready ALAN NOVAK
Smoke Detectors 7/14/2022 Not Ready for Inspection ALAN NOVAK
Final 8/26/2022 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 8/26/2022 Approved SORIN CIRSTOIU
Final 9/2/2022 OK for CofC GRANT WOODS