14255 W DICKENS ST 91423
Certificate Information: 14255 W DICKENS ST 91423
- Application / Permit
- 19016-10000-29710
- Plan Check / Job No.
- B19LA19783
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 3/31/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/7/2021
Permit Application Status History
| Submitted | 9/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | MANUEL MONTUFAR |
| Corrections Issued | 11/13/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 11/18/2019 | HANS SANTIAGO |
| Plan Check Approved | 12/20/2019 | MANUEL MONTUFAR |
| Issued | 3/31/2020 | LADBS |
| OK for CofC | 7/12/2021 | KENNETH ROBERTS |
| CofC Issued | 10/7/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/23/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Perluss Sheldon K; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2020 | Partial Inspection | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 6/10/2020 | Corrections Issued | DANIEL VARNUM |
| Structural Steel Frame | 6/10/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 6/10/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 6/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/25/2020 | Corrections Issued | JOE VELASQUEZ |
| Wood Frame | 7/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/31/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/27/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/3/2020 | Approved | JOE VELASQUEZ |
| Insulation | 9/24/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 9/24/2020 | Approved | JOE VELASQUEZ |
| Final | 5/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 5/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 6/14/2021 | Conditional Approval | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 6/14/2021 | Approved | KENNETH ROBERTS |
| Final | 7/12/2021 | OK for CofC | KENNETH ROBERTS |