7166 W MELROSE AVE 90046
Certificate Information: 7166 W MELROSE AVE 90046
- Application / Permit
- 19016-10000-29681
- Plan Check / Job No.
- B19LA19762
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Correct Floor area from previous C of O. Tenant Improvement to existing restaurant. (40' x 80')
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/16/2021
Permit Application Status History
| Submitted | 9/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2019 | SALVADOR QUINTANILLA |
| Corrections Issued | 9/17/2019 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/1/2019 | SALVADOR QUINTANILLA |
| Plan Check Approved | 1/28/2020 | SALVADOR QUINTANILLA |
| Issued | 2/4/2020 | LADBS |
| Permit Finaled | 3/16/2021 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Food Service Establishment | Cleared | 1/10/2020 | KENNETH BROWNE |
| Food establishment approval | Cleared | 1/28/2020 | LACDHS APPROVED |
Contact Information
| Contractor | Mayan - Pacific Construction; Lic. No.: 721304-B | 10969 S HOBART BLVD LOS ANGELES, CA 90047 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/11/2020 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 11/17/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Wood Frame | 11/17/2020 | Partial Approval | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 11/20/2020 | Approved | TIMOTHY BUXTON |
| Insulation | 12/29/2020 | Partial Approval | TIMOTHY BUXTON |
| Wood Frame | 12/29/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 1/5/2021 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 2/9/2021 | Approved | TIMOTHY BUXTON |
| Special/Order Compliance | 2/23/2021 | Approved | TIMOTHY BUXTON |
| Special/Order Compliance | 3/4/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Not Ready | TIMOTHY BUXTON |
| Final | 3/16/2021 | Permit Finaled | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 3/16/2021 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 3/16/2021 | Approved | TIMOTHY BUXTON |