4311 N COLFAX AVE 91604
Certificate Information: 4311 N COLFAX AVE 91604
- Application / Permit
- 19016-10000-29611
- Plan Check / Job No.
- B19LA19720
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH.93. INSTALL NEW SPECIAL STEEL MOMENT FRAMES
- Permit Issued
- Issued on 6/30/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/26/2023
Permit Application Status History
| Submitted | 9/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2019 | HANS SANTIAGO |
| Corrections Issued | 11/4/2019 | HANS SANTIAGO |
| Quality Review Completed | 11/6/2019 | SAI KHUM |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Applicant returned to address corrections | 12/11/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 1/16/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 4/23/2020 | HANS SANTIAGO |
| Plan Check Approved | 4/27/2020 | ANDREW SANTIAGO |
| Issued | 6/30/2022 | APPLICANT |
| OK for CofC | 5/24/2023 | KENNETH ROBERTS |
| CofC Issued | 7/26/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | BOK GOH |
| Housing rent stabilization | Cleared | 5/26/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2022 | Approved | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/18/2022 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/29/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 9/1/2022 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 9/7/2022 | Approved | KENNETH ROBERTS |
| Structural Steel Frame | 9/7/2022 | Approved | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 9/9/2022 | Conditional Approval | KENNETH ROBERTS |
| Wood Frame | 10/12/2022 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 10/13/2022 | Partial Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 10/14/2022 | Conditional Approval | KENNETH ROBERTS |
| Structural Steel Frame | 10/19/2022 | Approved | KENNETH ROBERTS |
| Deputy Wood Construction | 10/20/2022 | Conditional Approval | KENNETH ROBERTS |
| Wood Frame | 10/21/2022 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 11/15/2022 | Approved | KENNETH ROBERTS |
| Final | 5/24/2023 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Gas Company | KENNETH ROBERTS |
| Smoke Detectors | 5/24/2023 | Approved | KENNETH ROBERTS |