14102 W DELANO ST 91401

Certificate Information: 14102 W DELANO ST 91401

Application / Permit
19016-10000-29605
Plan Check / Job No.
B19LA19717
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 1 SPECIAL CANTILEVERED COLUMN SYSTEM (SCCS) WITH CONCRETE GRADE BEAM. WORKS AT TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofC Issued on 10/21/2021

Permit Application Status History

Submitted 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 ERWIN PASCUA
Corrections Issued 11/5/2019 ERWIN PASCUA
Quality Review Completed 11/7/2019 SAI KHUM
Building Plans Picked Up 11/15/2019 APPLICANT
Plan Check Approved 12/9/2019 ERWIN PASCUA
Issued 4/28/2021 APPLICANT
OK for CofC 8/23/2021 KENNETH ROBERTS
CofC Issued 10/21/2021 KENNETH ROBERTS

Permit Application Clearance Information

Housing rent stabilization Cleared 4/27/2021 MICHAEL SOTO

Contact Information

Contractor Retrofit 1; Lic. No.: 1003868-B 19326 VENTURA BLVD STE 200      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 6/11/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 6/11/2021 Corrections Issued JOE VELASQUEZ
Deputy Reinf. Concrete 6/15/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 6/15/2021 Approved JOE VELASQUEZ
Wood Frame 6/15/2021 Approved JOE VELASQUEZ
Insulation 6/17/2021 Approved JOE VELASQUEZ
Interior/Exterior Lathing 6/22/2021 Approved JOE VELASQUEZ
Final 8/4/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 8/4/2021 Not Ready for Inspection JOE VELASQUEZ
Final 8/9/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 8/9/2021 Not Ready for Inspection JOE VELASQUEZ
Final 8/23/2021 OK for CofC KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 8/23/2021 Approved KENNETH ROBERTS