1155 N MADISON AVE 90029

Certificate Information: 1155 N MADISON AVE 90029

Application / Permit
19016-10000-29567
Plan Check / Job No.
B19LA19693
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan 1004 :: Soft-Story seismic retrofit per LABC Chapter 93: USING (2) NEW SPECIAL STEEL CANT. COLUMNS AND HARDY PANELS.
Permit Issued
Issued on 5/4/2020
Issuing Office
Current Status
CofC Issued on 12/17/2020

Permit Application Status History

Submitted 10/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/6/2019 THOMAS SHERMAN
Corrections Issued 11/13/2019 THOMAS SHERMAN
Quality Review Completed 11/24/2019 HANS SANTIAGO
Plan Check Approved 1/24/2020 THOMAS SHERMAN
Issued 5/4/2020 APPLICANT
OK for CofC 12/9/2020 JONATHAN QUACH
CofC Issued 12/17/2020 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/9/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/9/2020 CELINA MORENO
Housing rent stabilization Cleared 5/4/2020 ISMAEL HERNANDEZ

Contact Information

Contractor K B Construction; Lic. No.: 925474-B 2021 W COMMONWEALTH AVE STE S      FULLERTON, CA 92833
Engineer Alexander,, Andy Joseph; Lic. No.: C84086 1730 E HOLLY AVE STE 107      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/8/2020 Approved MARK FERRARI
Excavation/Setback/Form/Re-Bar 7/28/2020 Corrections Issued MARK FERRARI
Excavation/Setback/Form/Re-Bar 8/12/2020 Approved MARK FERRARI
Wood Frame 8/24/2020 Partial Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 9/2/2020 Partial Inspection FELIX CEBALLOS
Deputy Wood Construction 9/3/2020 Partial Approval FELIX CEBALLOS
Floor/Roof Diaphrgm/Shear Wall 9/3/2020 Approved FELIX CEBALLOS
Interior/Exterior Lathing 9/15/2020 Approved MARK FERRARI
Final 10/6/2020 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Not Ready MARK FERRARI
Smoke Detectors 10/6/2020 Approved MARK FERRARI
Final 11/16/2020 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Not Ready JONATHAN QUACH
Final 12/9/2020 OK for CofC JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 12/9/2020 SGSOV Approved JONATHAN QUACH