9717 S HOLMES AVE 90002
Certificate Information: 9717 S HOLMES AVE 90002
- Application / Permit
- 19016-10000-29554
- Plan Check / Job No.
- B19LA19679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2) INTERIOR REMODEL OF (E) RESIDENCE (N) BATHROOM IN MASTER BEDROOM, NEW KITCHEN LAYOUT.
- Permit Issued
- Issued on 9/8/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/8/2022
Permit Application Status History
| Submitted | 9/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 9/24/2019 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/6/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 2/12/2020 | FARSHAD ALIMOHAMADI |
| Issued | 9/8/2020 | APPLICANT |
| Permit Finaled | 6/7/2022 | JOHN KLARIN |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 1/30/2020 | JOE LUCKEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/18/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 4/30/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/11/2022 | Corrections Issued | JOHN KLARIN |
| HVAC-Rough | 3/11/2022 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 3/11/2022 | Approved | JOHN KLARIN |
| Insulation | 3/15/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 3/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/18/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 4/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 4/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 6/2/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 6/2/2022 | Corrections Issued | JOHN KLARIN |
| Final | 6/7/2022 | Permit Finaled | JOHN KLARIN |
| Green Building Final | 6/7/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 6/7/2022 | Approved | JOHN KLARIN |
| Smoke Detectors | 6/7/2022 | Approved | JOHN KLARIN |