3460 W HYDE PARK BLVD 90043

Certificate Information: 3460 W HYDE PARK BLVD 90043

Application / Permit
19016-10000-29314
Plan Check / Job No.
B19LA19534
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan 990 :: Soft-Story seismic retrofit per LABC Chapter 93: Install 2 new STEEL SPECIAL CANTILEVER COLUMNS
Permit Issued
Issued on 5/19/2020
Issuing Office
Metro
Current Status
Issued on 5/19/2020

Permit Application Status History

Submitted 9/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 THOMAS SHERMAN
Corrections Issued 11/4/2019 THOMAS SHERMAN
Quality Review Completed 11/12/2019 HANS SANTIAGO
Plan Check Approved 1/7/2020 THOMAS SHERMAN
Issued 5/19/2020 LADBS

Permit Application Clearance Information

Historic Resource Verification Cleared 12/30/2019 GRACIELA ACOSTA
Redevelopment Project Area Cleared 12/30/2019 GRACIELA ACOSTA
Housing rent stabilization Cleared 3/16/2020 STEVEN HOFSTAD

Contact Information

Contractor Weinstein Construction Corporation; Lic. No.: 630439-B 15102 RAYMER STREET      VAN NUYS, CA 91405
Engineer Zohrevand,, Pedram; Lic. No.: C82328 21201 KITTRIDGE ST APT 9105      WOODLAND HILLS, CA 91303

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/5/2020 Corrections Issued JOEY BUCHANAN
Deputy Drilled-In Anchors 7/2/2020 Approved JOEY BUCHANAN
Deputy Steel/Welding 7/2/2020 Approved JOEY BUCHANAN
Deputy Other (see comments) 7/6/2020 Approved JOEY BUCHANAN
Deputy Other (see comments) 7/7/2020 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 7/9/2020 Corrections Issued VAHE KELEDJIAN
Pre-Inspection 7/13/2020 Approved JOEY BUCHANAN
Deputy Steel/Welding 7/15/2020 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 7/15/2020 Approved JOEY BUCHANAN
Structural Steel Frame 7/15/2020 Approved JOEY BUCHANAN
Wood Frame 7/15/2020 Not Ready for Inspection JOEY BUCHANAN
Structural Steel Frame 7/23/2020 Approved DARRYL ARNOLD
Wood Frame 7/23/2020 Approved DARRYL ARNOLD
Deputy Wood Construction 7/30/2020 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Approved JOEY BUCHANAN
Interior/Exterior Lathing 8/31/2020 Approved JOEY BUCHANAN
Final 10/15/2020 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 10/15/2020 Approved DARRYL ARNOLD