13226 W VANOWEN ST 91605

Certificate Information: 13226 W VANOWEN ST 91605

Application / Permit
19016-10000-29262
Plan Check / Job No.
B19LA19506
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CH.93 INSTALLING (3) Steel Special Cantilever Column and shear wall.
Permit Issued
Issued on 5/27/2020
Issuing Office
Current Status
CofC Issued on 11/12/2020

Permit Application Status History

Submitted 9/13/2019 APPLICANT
Assigned to Plan Check Engineer 10/23/2019 DANIEL SANJUAN
Corrections Issued 11/1/2019 DANIEL SANJUAN
Quality Review Completed 11/6/2019 HANS SANTIAGO
Building Plans Picked Up 11/7/2019 APPLICANT
Plan Check Approved 3/2/2020 DANIEL SANJUAN
Issued 5/27/2020 APPLICANT
OK for CofC 11/12/2020 ERNESTO CORRAL
CofC Issued 11/12/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 3/26/2020 PHILLIP MUNGUIA

Contact Information

Contractor Biayna Corp; Lic. No.: 998853-B 9751 WHEATLAND AVE      SUNLAND, CA 91040
Engineer Muradyan,, David; Lic. No.: S6232 10233 JOHANNA AVE      SUNLAND, CA 91040

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2020 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 7/20/2020 No Access for Inspection JOE VELASQUEZ
Excavation/Setback/Form/Re-Bar 7/22/2020 Approved JOE VELASQUEZ
Structural Steel Frame 7/22/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/22/2020 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 7/29/2020 Corrections Issued VAHE KELEDJIAN
Wood Frame 7/29/2020 Corrections Issued VAHE KELEDJIAN
Deputy Reinf. Concrete 7/30/2020 No Access for Inspection JOE VELASQUEZ
Wood Frame 8/5/2020 Partial Approval JOE VELASQUEZ
Structural Steel Frame 8/13/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/13/2020 Approved JOE VELASQUEZ
Interior/Exterior Lathing 9/11/2020 Approved JOE VELASQUEZ
Final 11/2/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 11/2/2020 Not Ready for Inspection JOE VELASQUEZ
Final 11/12/2020 OK for CofC ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved ERNESTO CORRAL
Smoke Detectors 11/12/2020 Approved ERNESTO CORRAL