13226 W VANOWEN ST 91605
Certificate Information: 13226 W VANOWEN ST 91605
- Application / Permit
- 19016-10000-29262
- Plan Check / Job No.
- B19LA19506
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH.93 INSTALLING (3) Steel Special Cantilever Column and shear wall.
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Current Status
- CofC Issued on 11/12/2020
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | DANIEL SANJUAN |
| Corrections Issued | 11/1/2019 | DANIEL SANJUAN |
| Quality Review Completed | 11/6/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 11/7/2019 | APPLICANT |
| Plan Check Approved | 3/2/2020 | DANIEL SANJUAN |
| Issued | 5/27/2020 | APPLICANT |
| OK for CofC | 11/12/2020 | ERNESTO CORRAL |
| CofC Issued | 11/12/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/26/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Biayna Corp; Lic. No.: 998853-B | 9751 WHEATLAND AVE SUNLAND, CA 91040 |
| Engineer | Muradyan,, David; Lic. No.: S6232 | 10233 JOHANNA AVE SUNLAND, CA 91040 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/20/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 7/22/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 7/22/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/22/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/29/2020 | Corrections Issued | VAHE KELEDJIAN |
| Wood Frame | 7/29/2020 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Reinf. Concrete | 7/30/2020 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/5/2020 | Partial Approval | JOE VELASQUEZ |
| Structural Steel Frame | 8/13/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/13/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 9/11/2020 | Approved | JOE VELASQUEZ |
| Final | 11/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/2/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 11/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 11/12/2020 | OK for CofC | ERNESTO CORRAL |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | ERNESTO CORRAL |
| Smoke Detectors | 11/12/2020 | Approved | ERNESTO CORRAL |