6430 W SUNSET BLVD 90028
Certificate Information: 6430 W SUNSET BLVD 90028
- Application / Permit
- 19016-10000-29121
- Plan Check / Job No.
- B19LA19403
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- PROPOSED CHANGE OF USE FROM OFFICE TO GYM AND TENANT IMPROVEMENT (APPROX. 2,355 SF) WORK TO INCLUDE NEW RESTROOMS WITH SHOWERS, WALLS AND FINISHES. ***see comments***
- Permit Issued
- Issued on 1/2/2020
- Issuing Office
- Metro
- Current Status
- Issued on 1/2/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2019 | SINA KHOSRAVI |
| Corrections Issued | 9/20/2019 | SINA KHOSRAVI |
| Applicant returned to address corrections | 10/11/2019 | SINA KHOSRAVI |
| Plan Check Approved | 10/24/2019 | KEVIN MORALES |
| Issued | 1/2/2020 | LADBS |
Permit Application Clearance Information
| ZA Case | Cleared | 10/11/2019 | LATANYA ROUX |
| ZA Case | Cleared | 10/11/2019 | LATANYA ROUX |
| "D" conditions | Cleared | 10/22/2019 | ANNA VAN |
| Project located in CRA area | Cleared | 10/22/2019 | JIM URQUHART |
| ZA Case | Cleared | 10/22/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2019 | CELINA MORENO |
| Sewer availability | Cleared | 10/24/2019 | CELINA MORENO |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: C21090 | 1524 1ST STREET MANHATTAN BEACH, CA 90266 |
| Contractor | G C X Llc; Lic. No.: 1045286-B | 29209 LARO DRIVE AGOURA HILLS, CA 91301 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/31/2020 | Corrections Issued | GRANT WOODS |
| Footing/Foundation/Slab | 1/31/2020 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 2/6/2020 | Partial Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 2/21/2020 | Approved | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 3/4/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| Insulation | 3/13/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Drywall Nailing | 3/19/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Drywall Nailing | 3/23/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 4/1/2020 | Conditional Approval | VAHE KELEDJIAN |
| T-Bar Ceiling | 4/22/2020 | Approved | LANNY MERRICK |
| Drywall Nailing | 4/27/2020 | Not Ready for Inspection | LANNY MERRICK |
| Light Gage Steel Frame | 4/27/2020 | Conditional Approval | LANNY MERRICK |
| Drywall Nailing | 4/28/2020 | Approved | LANNY MERRICK |
| Light Gage Steel Frame | 4/28/2020 | Partial Approval | LANNY MERRICK |
| Final | 5/15/2020 | Partial Approval | LANNY MERRICK |
| Reinforced Concrete Frame | 5/15/2020 | Approved | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 5/15/2020 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 5/15/2020 | Approved | LANNY MERRICK |
| Final | 3/25/2022 | Conditional Approval | JONATHAN QUACH |