616 W NEW DEPOT ST 90012
Certificate Information: 616 W NEW DEPOT ST 90012
- Application / Permit
- 19016-10000-29102
- Plan Check / Job No.
- B19LA19391
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 1009 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new SCCS.
- Permit Issued
- Issued on 7/30/2020
- Issuing Office
- Current Status
- CofC Issued on 11/5/2021
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | VARAND SARKISIAN |
| Corrections Issued | 10/28/2019 | VARAND SARKISIAN |
| Quality Review Completed | 11/4/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/13/2020 | VARAND SARKISIAN |
| Plan Check Approved | 7/17/2020 | VARAND SARKISIAN |
| Issued | 7/30/2020 | APPLICANT |
| OK for CofC | 11/5/2021 | MARK FERRARI |
| CofC Issued | 11/5/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 7/14/2020 | DAVID URITA |
| Housing rent stabilization | Cleared | 7/27/2020 | MICHAEL SOTO |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Kazarians,, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 9/16/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/23/2020 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/23/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 10/26/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 10/30/2020 | No Access for Inspection | MARK FERRARI |
| Wood Frame | 10/30/2020 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 11/4/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 11/4/2020 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 12/1/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 12/1/2020 | Approved | MARK FERRARI |
| Wood Frame | 12/1/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 12/10/2020 | Approved | DARRYL ARNOLD |
| Final | 8/25/2021 | Conditional Approval | MARK FERRARI |
| METHANE-Final | 8/25/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 8/25/2021 | Approved | MARK FERRARI |
| Final | 11/5/2021 | OK for CofC | MARK FERRARI |