- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 1/19/2023
- Issuing Office
- Current Status
- CofC Issued on 12/16/2025
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | HANS SANTIAGO |
| Corrections Issued | 10/28/2019 | HANS SANTIAGO |
| Quality Review Completed | 10/30/2019 | SAI KHUM |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Plan Check Approved | 4/16/2020 | ANDREW SANTIAGO |
| Refund in Progress | 8/20/2020 | SELENIA GARCIA |
| Refund Closed | 8/20/2020 | SELENIA GARCIA |
| Reactivate - Status Void | 8/20/2020 | SELENIA GARCIA |
| Issued | 1/19/2023 | APPLICANT |
| OK for CofC | 12/16/2025 | ERNESTO CORRAL |
| CofC Issued | 12/16/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/10/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/10/2020 | WALTER RAMIREZ |
| Housing rent stabilization | Cleared | 11/28/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Farmand,, Anthony E; Lic. No.: C62595 | 2372 MORSE AVE STE 137 IRVINE, CA 92614 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/14/2023 | Conditional Approval | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 9/14/2023 | Partial Inspection | VAHE KELEDJIAN |
| Pre-Inspection | 9/14/2023 | Partial Inspection | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 9/21/2023 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/28/2023 | Conditional Approval | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 9/28/2023 | Partial Approval | VAHE KELEDJIAN |
| Deputy Steel/Welding | 10/23/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/27/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/30/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 11/3/2023 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 11/9/2023 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 11/9/2023 | Approved | JACOB MYERS |
| Deputy Steel/Welding | 11/15/2023 | Approved | JACOB MYERS |
| Final | 11/15/2023 | Not Ready for Inspection | JACOB MYERS |
| METHANE-Final | 11/15/2023 | Not Ready for Inspection | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Not Ready | JACOB MYERS |
| Smoke Detectors | 11/15/2023 | Not Ready for Inspection | JACOB MYERS |
| Final | 11/30/2023 | Partial Approval | JACOB MYERS |
| METHANE-Final | 11/30/2023 | Approved | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 11/30/2023 | Approved | JACOB MYERS |
| Final | 12/16/2025 | OK for CofC | ERNESTO CORRAL |