5509 N KLUMP AVE 91601

Certificate Information: 5509 N KLUMP AVE 91601

Application / Permit
19016-10000-29033
Plan Check / Job No.
B19LA19340
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL (2) SCCS.
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofC Issued on 7/12/2021

Permit Application Status History

Submitted 9/12/2019 APPLICANT
Assigned to Plan Check Engineer 10/23/2019 DANIEL YIP
Corrections Issued 10/28/2019 DANIEL YIP
Quality Review Completed 11/4/2019 SAI KHUM
Building Plans Picked Up 11/5/2019 APPLICANT
Applicant returned to address corrections 1/2/2020 DANIEL YIP
Plan Check Approved 1/9/2020 DANIEL YIP
Issued 2/19/2021 APPLICANT
OK for CofC 6/21/2021 JOE VELASQUEZ
CofC Issued 7/12/2021 RICKEY JACKSON

Permit Application Clearance Information

Project located in CRA area Cleared 1/3/2020 GRACIELA ACOSTA
Housing rent stabilization Cleared 2/17/2021 STEVEN HOFSTAD

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 2/25/2021 Not Ready for Inspection JOE VELASQUEZ
Insulation 2/26/2021 Partial Approval JOE VELASQUEZ
Deputy Drilled-In Anchors 3/2/2021 Approved JOE VELASQUEZ
Deputy Wood Construction 3/3/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 3/4/2021 Approved JOE VELASQUEZ
Deputy Reinf. Concrete 3/5/2021 No Access for Inspection JOE VELASQUEZ
Structural Steel Frame 3/25/2021 Approved JOE VELASQUEZ
Wood Frame 3/25/2021 Approved JOE VELASQUEZ
Interior/Exterior Lathing 3/31/2021 Not Ready for Inspection JOE VELASQUEZ
Interior/Exterior Lathing 4/5/2021 Not Ready for Inspection JOE VELASQUEZ
Interior/Exterior Lathing 4/6/2021 Approved JOE VELASQUEZ
Final 6/3/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 6/3/2021 Not Ready for Inspection JOE VELASQUEZ
Final 6/21/2021 OK for CofC JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 6/21/2021 SGSOV Approved JOE VELASQUEZ
Smoke Detectors 6/21/2021 Approved JOE VELASQUEZ