1042 S OXFORD AVE 90006
Certificate Information: 1042 S OXFORD AVE 90006
- Application / Permit
- 19016-10000-28973
- Plan Check / Job No.
- B19LA19307
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH.93 USING STEEL CANTILEVER COLUMNS AND WOOD SHEAR WALLS
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 9/11/2024
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | HANS SANTIAGO |
| Corrections Issued | 10/28/2019 | HANS SANTIAGO |
| Quality Review Completed | 10/30/2019 | SAI KHUM |
| Building Plans Picked Up | 11/5/2019 | APPLICANT |
| Plan Check Approved | 1/15/2020 | ANDREW SANTIAGO |
| Issued | 4/18/2022 | APPLICANT |
| OK for CofC | 9/11/2024 | DARRYL ARNOLD |
| CofC Issued | 9/11/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 1/10/2020 | GRACIELA ACOSTA |
| Housing rent stabilization | Cleared | 3/17/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Together Construction; Lic. No.: 1018331-B | 12252 MEADOW DR ARTESIA, CA 90701 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/3/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 5/10/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 6/1/2022 | Conditional Approval | ERNESTO CORRAL |
| Reinforced Concrete Frame | 6/6/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 6/6/2022 | Conditional Approval | DARRYL ARNOLD |
| Reinforced Concrete Frame | 6/8/2022 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 6/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/10/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 6/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 6/24/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/30/2022 | Conditional Approval | DARRYL ARNOLD |
| Wall Anchors | 8/30/2022 | Conditional Approval | DARRYL ARNOLD |
| Wall Anchors | 10/27/2022 | Corrections Issued | DARRYL ARNOLD |
| Wall Anchors | 11/1/2022 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/17/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Wall Anchors | 11/17/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/22/2022 | Corrections Issued | DARRYL ARNOLD |
| Wall Anchors | 11/22/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/9/2022 | Corrections Issued | DARRYL ARNOLD |
| Wall Anchors | 12/9/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/16/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Wall Anchors | 12/16/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/21/2022 | Not Ready for Inspection | VAHE KELEDJIAN |
| Wall Anchors | 12/21/2022 | Not Ready for Inspection | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 12/23/2022 | Corrections Issued | VAHE KELEDJIAN |
| Wall Anchors | 1/19/2023 | Corrections Issued | DARRYL ARNOLD |
| Deputy Wood Construction | 2/6/2023 | Conditional Approval | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 3/7/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Special/Order Compliance | 3/8/2023 | Corrections Issued | DARRYL ARNOLD |
| Final | 3/24/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 3/24/2023 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 3/24/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 3/31/2023 | Conditional Approval | DARRYL ARNOLD |
| Wall Anchors | 3/31/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/4/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/19/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| METHANE-Final | 4/19/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Not Ready | VAHE KELEDJIAN |
| Smoke Detectors | 4/19/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Deputy Wood Construction | 8/13/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 8/14/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 9/11/2024 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 9/11/2024 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 9/11/2024 | Approved | DARRYL ARNOLD |