10603 W TABOR ST 90034
Certificate Information: 10603 W TABOR ST 90034
- Application / Permit
- 19016-10000-28967
- Plan Check / Job No.
- B19LA19303
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 1008 :: Soft-Story seismic retrofit per LABC Chapter 93: install (3) steel special cantilevered columns and plywood shear wall.
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/28/2021
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | THOMAS SHERMAN |
| Corrections Issued | 10/29/2019 | THOMAS SHERMAN |
| Quality Review Completed | 11/4/2019 | HANS SANTIAGO |
| Plan Check Approved | 1/31/2020 | THOMAS SHERMAN |
| Issued | 6/4/2020 | LADBS |
| OK for CofC | 1/11/2021 | GRANT WOODS |
| CofC Issued | 1/28/2021 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/22/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Simzee Construction & Development Inc; Lic. No.: 924904-B | 14402 HAYNES ST STE 201 VAN NUYS, CA 91401 |
| Engineer | Labib,, Youhanna T; Lic. No.: NA4549 | , |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2020 | Approved | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 10/1/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 10/5/2020 | Approved | GRANT WOODS |
| Deputy Wood Construction | 10/29/2020 | Conditional Approval | GRANT WOODS |
| Wood Frame | 11/5/2020 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 12/30/2020 | Conditional Approval | GRANT WOODS |
| Final | 1/11/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/11/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 1/11/2021 | Approved | GRANT WOODS |