3754 S VINTON AVE 90034

Certificate Information: 3754 S VINTON AVE 90034

Application / Permit
19016-10000-28946
Plan Check / Job No.
B19LA19288
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CH.93. INSTALL STEEL CANTILEVER COLUMNS
Permit Issued
Issued on 3/5/2020
Issuing Office
Metro
Current Status
CofC Issued on 10/2/2020

Permit Application Status History

Submitted 9/12/2019 APPLICANT
Assigned to Plan Check Engineer 10/23/2019 HANS SANTIAGO
Corrections Issued 10/28/2019 HANS SANTIAGO
Quality Review Completed 10/30/2019 SAI KHUM
Building Plans Picked Up 11/6/2019 APPLICANT
Plan Check Approved 1/13/2020 ANDREW SANTIAGO
Issued 3/5/2020 LADBS
OK for CofC 9/25/2020 TIMOTHY BUXTON
CofC Issued 10/2/2020 TED RIES

Permit Application Clearance Information

Housing rent stabilization Cleared 3/3/2020 MICHAEL GREGERSON

Contact Information

Contractor Lockwood Engineering; Lic. No.: 1016915-B 9663 SANTA MONICA BLVD #745      BEVERLY HILLS, CA 90210
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 5104 GARDEN GROVE      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/14/2020 Approved GRANT WOODS
Deputy Drilled-In Anchors 8/20/2020 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 8/24/2020 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 8/25/2020 Conditional Approval GRANT WOODS
Reinforced Concrete Frame 8/25/2020 Not Ready for Inspection GRANT WOODS
Structural Steel Frame 8/25/2020 Not Ready for Inspection GRANT WOODS
Wood Frame 8/25/2020 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 8/28/2020 Conditional Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/1/2020 Approved GRANT WOODS
Structural Steel Frame 9/1/2020 Approved GRANT WOODS
Wood Frame 9/1/2020 Approved GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 9/3/2020 Conditional Approval GRANT WOODS
Interior/Exterior Lathing 9/8/2020 Approved GRANT WOODS
Final 9/14/2020 Partial Inspection GRANT WOODS
METHANE-Final 9/14/2020 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Not Ready GRANT WOODS
Smoke Detectors 9/14/2020 Not Ready for Inspection GRANT WOODS
Final 9/25/2020 OK for CofC TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 9/25/2020 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 9/25/2020 Approved TIMOTHY BUXTON