7310 S HOOVER ST 90044
Certificate Information: 7310 S HOOVER ST 90044
- Application / Permit
- 19016-10000-28934
- Plan Check / Job No.
- B19LA19277
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH.93; INSTALLING (2) SCCS AND PLYWOOD THREE (3) WOOD SHEAR WALLS
- Permit Issued
- Issued on 2/14/2024
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/23/2025
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | DANIEL YIP |
| Corrections Issued | 10/28/2019 | DANIEL YIP |
| Quality Review Completed | 11/4/2019 | SAI KHUM |
| Building Plans Picked Up | 11/26/2019 | APPLICANT |
| Plan Check Approved | 7/14/2023 | BIDYUT RATH |
| Issued | 2/14/2024 | APPLICANT |
| OK for CofC | 12/18/2025 | DARRYL ARNOLD |
| CofC Issued | 12/23/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 3/3/2023 | SAI KHUM |
| Community Plan Implem. Overlay | Cleared | 3/9/2023 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 3/21/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2023 | CELINA MORENO |
| Housing rent stabilization | Cleared | 1/25/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Saddick Construction Company Inc; Lic. No.: 751864-B | 1601 COLINA DR GLENDALE, CA 91208 |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/31/2025 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/7/2025 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 8/12/2025 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 8/27/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 9/12/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 9/12/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/12/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 9/12/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 10/15/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/15/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/18/2025 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 12/18/2025 | Approved | DARRYL ARNOLD |