- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALLSIMPSON MOMENT FRAME.
- Permit Issued
- Issued on 2/25/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/7/2021
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | MANUEL MONTUFAR |
| Corrections Issued | 11/13/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 11/18/2019 | HANS SANTIAGO |
| Plan Check Approved | 1/10/2020 | MANUEL MONTUFAR |
| Issued | 2/25/2020 | LADBS |
| OK for CofC | 7/9/2020 | JOE VELASQUEZ |
| CofC Issued | 4/7/2021 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2019 | ELENA LOPEZ |
| Housing rent stabilization | Cleared | 2/24/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Dldp Companies Inc; Lic. No.: 717286-B | 9909 CANOGA AVE SUITE G CHATSWORTH, CA 91311 |
| Engineer | Puliyadi,, Senthilnath Surendran; Lic. No.: NA71630 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/5/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 5/5/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/5/2020 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/6/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 5/6/2020 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/21/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/3/2020 | Approved | JOE VELASQUEZ |
| Drywall Nailing | 6/24/2020 | Approved | JOE VELASQUEZ |
| Final | 7/9/2020 | OK for CofC | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/9/2020 | SGSOV Approved | JOE VELASQUEZ |
| Smoke Detectors | 7/9/2020 | Approved | JOE VELASQUEZ |