4658 N COLFAX AVE 91602

Certificate Information: 4658 N COLFAX AVE 91602

Application / Permit
19016-10000-28822
Plan Check / Job No.
B19LA19177
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 2 SPECIAL CANTILEVERED COLUMN SYSTEM (SCCS) WITH CONCRETE GRADE BEAM. WORKS AT TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
Permit Issued
Issued on 1/29/2020
Issuing Office
Metro
Current Status
CofC Issued on 10/21/2020

Permit Application Status History

Submitted 9/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/16/2019 ERWIN PASCUA
Corrections Issued 10/20/2019 ERWIN PASCUA
Quality Review Completed 10/24/2019 SAI KHUM
Building Plans Picked Up 10/31/2019 APPLICANT
Plan Check Approved 12/9/2019 ERWIN PASCUA
Issued 1/29/2020 LADBS
OK for CofC 10/21/2020 ERNESTO CORRAL
CofC Issued 10/21/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 1/8/2020 MICHAEL GREGERSON
Specific Plan Cleared 1/29/2020 ANNA VIDAL
ZI Cleared 1/29/2020 ANNA VIDAL

Contact Information

Contractor Retrofit 1; Lic. No.: 1003868-B 19326 VENTURA BLVD SUITE 200      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2020 Partial Inspection FRED WOHLFARTH
Footing/Foundation/Slab 3/9/2020 Approved FRED WOHLFARTH
Structural Steel Frame 3/9/2020 Approved FRED WOHLFARTH
Wood Frame 3/9/2020 Conditional Approval FRED WOHLFARTH
Deputy Steel/Welding 3/10/2020 Conditional Approval FRED WOHLFARTH
Interior/Exterior Lathing 3/17/2020 Corrections Issued FRED WOHLFARTH
Final 4/22/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 4/22/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 4/22/2020 Not Ready for Inspection JOE VELASQUEZ
Final 5/7/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 5/7/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 5/7/2020 Not Ready for Inspection JOE VELASQUEZ
Final 10/16/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 10/16/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 10/16/2020 Not Ready for Inspection JOE VELASQUEZ
Final 10/21/2020 OK for CofC ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Approved ERNESTO CORRAL
Smoke Detectors 10/21/2020 Approved ERNESTO CORRAL