6709 N INDEPENDENCE AVE 91303

Certificate Information: 6709 N INDEPENDENCE AVE 91303

Application / Permit
19016-10000-28465
Plan Check / Job No.
B19LA18984
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(7) Parking Garage
Work Description
NEW 6-STORY TYPE IIA OPEN PARKING STRUCTURE WITH ROOFTOP PARKING ASSESSORY TO APARTMENT BUILDING. see comment.
Permit Issued
Issued on 8/24/2020
Issuing Office
Current Status
CofO Issued on 2/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 TSE MING HUANG
Disabled Access Plans Picked Up 10/10/2019 APPLICANT
Corrections Issued 10/14/2019 TSE MING HUANG
Quality Review Completed 10/26/2019 STANLEY RAAP
Applicant returned to address corrections 5/5/2020 TSE MING HUANG
Green Plans Picked Up 7/21/2020 APPLICANT
Plan Check Approved 8/21/2020 TSE MING HUANG
Issued 8/24/2020 APPLICANT
Building Plans Picked Up 9/21/2020 APPLICANT
TCO Issued (Expire Date: 07-31-2023) 2/1/2023 RICKEY JACKSON
CofO in Progress 2/15/2024 CAMERON CHABAN
Permit Finaled 2/15/2024 RICKEY JACKSON
CofO Issued 2/15/2024 RICKEY JACKSON
Permit Finaled 2/15/2024 RICKEY JACKSON

Permit Application Clearance Information

Green Code Cleared 2/10/2020 TSE MING HUANG
CPC Cleared 4/2/2020 TERRI OSBORNE
ZA Case Cleared 4/2/2020 TERRI OSBORNE
Specific Plan Cleared 4/21/2020 TERRI OSBORNE
Driveway location Cleared 4/22/2020 SHEILA AHORAIAN
Eng Process Fee Ord 176,300 Cleared 5/7/2020 GUILLERMO PETRA
Low Impact Development Cleared 6/2/2020 ANDRES COVARRUBIAS
Sewer availability Cleared 6/17/2020 GABRIEL ROBLES
DAS Clearance Cleared 6/25/2020 TSE MING HUANG
Address approval Cleared 7/7/2020 HOWARD COOPER
Building over 3-story or 36-ft Cleared 7/8/2020 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 7/15/2020 GUILLERMO PETRA
Fire Marshall Fire Life Safety Cleared 7/22/2020 DOMINIQUE MEDINA
Miscellaneous Cleared 8/4/2020 TERRI OSBORNE
ZI Cleared 8/4/2020 TERRI OSBORNE
Highway dedication Cleared 8/5/2020 ABDULLAH SADOZAI
Permit Cleared 8/5/2020 ABDULLAH SADOZAI

Contact Information

Architect Gaffney,, Steven Patrick; Lic. No.: C19676 2408 NEWPORT BLVD      NEWPORT BEACH, CA 92663
Contractor Fairfield Development L P; Lic. No.: 951612-B 5510 MOREHOUSE DRIVE SUITE 200      SAN DIEGO, CA 92121
Contractor Kount On Us Carpet Cleaning Restoration; Lic. No.: 961612-C15 13287 TOPOCK ROAD      APPLE VALLEY, CA 92308
Engineer Bondy,, Kenneth Dirk; Lic. No.: S3921 27575 FARGO RD      LAGUNA HILLS, CA 92653
Engineer Brotchie,, David Ian; Lic. No.: C62005 95-717 KELEWAA ST      MILILANI, HI 96789
Engineer Varela,, Gregorio; Lic. No.: C81201 1108 S ADAMS ST      GLENDALE, CA 91205

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2020 Approved ALAN NOVAK
Pre-Inspection 9/25/2020 Partial Inspection DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 9/30/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 10/1/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/8/2020 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/8/2020 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 10/8/2020 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/9/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/15/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 10/16/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 10/20/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 10/23/2020 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 10/23/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 10/28/2020 Approved HAMID PISHEHVAR
Green Building Rough 11/13/2020 Partial Approval HAMID PISHEHVAR
Reinforced Concrete Frame 11/13/2020 Partial Approval HAMID PISHEHVAR
Deputy Pre-Stress Concrete 11/24/2020 Conditional Approval RICKEY JACKSON
Deputy Pre-Stress Concrete 12/2/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/2/2020 Partial Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 12/3/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 12/4/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 12/7/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 12/8/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/8/2020 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 12/8/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/9/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/9/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 12/10/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 12/11/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/11/2020 Approved HAMID PISHEHVAR
Green Building Rough 12/11/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Masonry Frame 12/11/2020 Partial Approval HAMID PISHEHVAR
Structural Steel Frame 12/11/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Concrete 12/14/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/14/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/15/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/15/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 12/16/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/16/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 12/17/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/17/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 12/18/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/18/2020 Approved HAMID PISHEHVAR
Green Building Rough 12/18/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Concrete Frame 12/18/2020 Partial Approval HAMID PISHEHVAR
Reinforced Masonry Frame 12/18/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Concrete 12/22/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 12/22/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 1/5/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/6/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/7/2021 Approved HAMID PISHEHVAR
Reinforced Concrete Frame 1/7/2021 Partial Approval ROBERT DAVIS
Deputy Pre-Stress Concrete 1/8/2021 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 1/11/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 1/11/2021 Conditional Approval ROBERT DAVIS
Deputy Pre-Stress Concrete 1/12/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/12/2021 Approved HAMID PISHEHVAR
Green Building Rough 1/12/2021 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Concrete Frame 1/12/2021 Partial Approval HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/13/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/13/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/14/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/14/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/15/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/15/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/19/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/19/2021 Approved HAMID PISHEHVAR
Green Building Rough 1/19/2021 Partial Approval HAMID PISHEHVAR
Reinforced Concrete Frame 1/19/2021 Partial Approval HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/20/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/20/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/21/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/21/2021 Approved HAMID PISHEHVAR
Structural Steel Frame 1/21/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/22/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/22/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/25/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 1/25/2021 Approved HAMID PISHEHVAR
Green Building Rough 1/25/2021 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Masonry Frame 1/25/2021 Not Ready for Inspection HAMID PISHEHVAR
Deputy Pre-Stress Concrete 1/26/2021 No Access for Inspection CAMERON CHABAN
Deputy Reinf. Masonry 1/26/2021 No Access for Inspection CAMERON CHABAN
Deputy Pre-Stress Concrete 2/2/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 2/2/2021 Approved JOHN KITCKO
Green Building Rough 2/2/2021 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 2/2/2021 Not Ready for Inspection JOHN KITCKO
Deputy Pre-Stress Concrete 2/3/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/3/2021 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 2/3/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/4/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 2/4/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 2/5/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/5/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 2/5/2021 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 2/5/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/8/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/8/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 2/9/2021 Partial Approval CAMERON CHABAN
Structural Steel Frame 2/9/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/10/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/10/2021 Conditional Approval CAMERON CHABAN
Structural Steel Frame 2/10/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/11/2021 Approved CAMERON CHABAN
Deputy Reinf. Masonry 2/11/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/12/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/12/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 2/12/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 2/12/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/16/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/16/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/16/2021 Conditional Approval CAMERON CHABAN
Structural Steel Frame 2/16/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/17/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/17/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/18/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/18/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 2/18/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 2/18/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/19/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/19/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/22/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/22/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 2/22/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 2/22/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/23/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/23/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/24/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/24/2021 Conditional Approval CAMERON CHABAN
Structural Steel Frame 2/24/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 2/25/2021 Approved ROBERT DAVIS
Deputy Reinf. Masonry 2/25/2021 Approved ROBERT DAVIS
Green Building Rough 2/25/2021 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 2/25/2021 Partial Approval ROBERT DAVIS
Deputy Pre-Stress Concrete 2/26/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/26/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/1/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/1/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/2/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/2/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 3/2/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 3/2/2021 Partial Inspection CAMERON CHABAN
Structural Steel Frame 3/2/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/3/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/3/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/4/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/4/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/5/2021 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 3/8/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/8/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 3/8/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 3/8/2021 Partial Approval CAMERON CHABAN
Reinforced Masonry Frame 3/8/2021 Partial Approval CAMERON CHABAN
Structural Steel Frame 3/8/2021 Conditional Approval CAMERON CHABAN
Drywall Nailing 3/9/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 3/9/2021 Partial Inspection CAMERON CHABAN
Green Building Rough 3/10/2021 Partial Inspection CAMERON CHABAN
Reinforced Masonry Frame 3/10/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/11/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/11/2021 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 3/11/2021 Partial Inspection CAMERON CHABAN
Structural Steel Frame 3/11/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/12/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/12/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/15/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/15/2021 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/15/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/16/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/16/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/19/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/19/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 3/19/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 3/19/2021 Order to Comply Issued CAMERON CHABAN
Deputy Pre-Stress Concrete 3/22/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 3/22/2021 Approved HAMID PISHEHVAR
Piling/Pier/Caisson 3/22/2021 Partial Approval HAMID PISHEHVAR
Structural Steel Frame 3/22/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 3/23/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/23/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/24/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/24/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 3/24/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/25/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/25/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/26/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/26/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 3/26/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 3/26/2021 Partial Approval CAMERON CHABAN
Structural Steel Frame 3/26/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 3/30/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/30/2021 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 3/31/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/31/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 3/31/2021 Partial Inspection CAMERON CHABAN
Masonry Wall/Backfill 3/31/2021 Partial Approval CAMERON CHABAN
Reinforced Concrete Frame 3/31/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/1/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/1/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/5/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/5/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/5/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/5/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 4/5/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 4/5/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/6/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/6/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/6/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 4/6/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/7/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/7/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/7/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/8/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/8/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/8/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 4/8/2021 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 4/8/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/9/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/9/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/9/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/12/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/12/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/14/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 4/14/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/15/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/15/2021 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 4/19/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/19/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 4/19/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 4/19/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/20/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/20/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/21/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/21/2021 Conditional Approval CAMERON CHABAN
Structural Steel Frame 4/21/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/22/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/22/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/23/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/23/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/26/2021 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 4/26/2021 Conditional Approval JEFFREY FULTON
Green Building Rough 4/26/2021 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 4/26/2021 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 4/26/2021 Partial Inspection JEFFREY FULTON
Structural Steel Frame 4/26/2021 Not Ready for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/27/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/27/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/28/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/28/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 4/28/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 4/29/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/29/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/29/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 5/3/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 5/3/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/4/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/4/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/5/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/5/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 5/5/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 5/5/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/6/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/6/2021 Conditional Approval JEFFREY DURAN
Reinforced Masonry Frame 5/7/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/10/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/10/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 5/10/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/11/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/11/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/12/2021 Partial Inspection CAMERON CHABAN
Deputy Reinf. Masonry 5/12/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/13/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/13/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 5/13/2021 Partial Approval CAMERON CHABAN
Green Building Rough 5/13/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 5/13/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/14/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/14/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/17/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/17/2021 Conditional Approval CAMERON CHABAN
Structural Steel Frame 5/17/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/18/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 5/18/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 5/19/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 5/19/2021 Approved HAMID PISHEHVAR
Drywall Nailing 5/19/2021 Not Ready for Inspection HAMID PISHEHVAR
Green Building Rough 5/19/2021 Partial Approval HAMID PISHEHVAR
Reinforced Concrete Frame 5/19/2021 Partial Approval HAMID PISHEHVAR
Deputy Pre-Stress Concrete 5/20/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/20/2021 Conditional Approval CAMERON CHABAN
Reinforced Masonry Frame 5/20/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/24/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/24/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/25/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 5/25/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 5/26/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 5/26/2021 Approved HAMID PISHEHVAR
Green Building Rough 5/26/2021 Partial Approval HAMID PISHEHVAR
Reinforced Concrete Frame 5/26/2021 Partial Approval HAMID PISHEHVAR
Deputy Pre-Stress Concrete 5/27/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 5/27/2021 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 5/27/2021 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 5/28/2021 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 5/28/2021 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/1/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 6/1/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 6/2/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 6/2/2021 Partial Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 6/3/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 6/4/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/7/2021 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/8/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 6/8/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 6/8/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/9/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/17/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 6/18/2021 Conditional Approval ALAN NOVAK
Green Building Rough 6/18/2021 Approved ALAN NOVAK
Reinforced Concrete Frame 6/18/2021 Partial Approval ALAN NOVAK
Masonry Wall/Backfill 6/22/2021 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 6/22/2021 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 6/23/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/24/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 6/25/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/1/2021 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 7/1/2021 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 7/7/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 7/8/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 7/9/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 7/14/2021 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 7/15/2021 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/15/2021 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 7/15/2021 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 7/16/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/20/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 7/20/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 7/21/2021 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 7/21/2021 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 7/22/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/23/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 7/23/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 7/28/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/29/2021 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 7/29/2021 Conditional Approval DANIEL VARNUM
Reinforced Concrete Frame 7/29/2021 No Access for Inspection DANIEL VARNUM
Deputy Steel/Welding 7/30/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 7/30/2021 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 8/4/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/5/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/6/2021 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 8/9/2021 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 8/10/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/11/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/12/2021 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 8/13/2021 Conditional Approval KENNETH ROBERTS
Deputy Steel/Welding 8/16/2021 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 8/17/2021 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/18/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/18/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/19/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/20/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/23/2021 Conditional Approval CAMERON CHABAN
Protected Tree Letter 8/23/2021 Partial Inspection CAMERON CHABAN
Deputy Steel/Welding 8/24/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/25/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/26/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/27/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/30/2021 Conditional Approval KENNETH ROBERTS
Deputy Steel/Welding 8/31/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 9/1/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 9/2/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 9/3/2021 Conditional Approval CAMERON CHABAN
Deputy Pre-Stress Concrete 9/8/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/8/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 9/17/2021 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 9/20/2021 Conditional Approval ALAN NOVAK
Reinforced Masonry Frame 1/14/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 2/9/2022 Partial Approval CAMERON CHABAN
Insulation 2/9/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 4/1/2022 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval CAMERON CHABAN
Insulation 4/1/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 4/4/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 8/18/2022 Approved CAMERON CHABAN
Light Gage Steel Frame 8/18/2022 Approved CAMERON CHABAN
Special/Order Compliance 12/16/2022 Conditional Approval CAMERON CHABAN
Special/Order Compliance 5/30/2023 Not Ready for Inspection BRIAN KELLY
Final 6/30/2023 Not Ready for Inspection CAMERON CHABAN
Green Building Final 6/30/2023 Approved CAMERON CHABAN
Reinforced Concrete Frame 6/30/2023 Approved CAMERON CHABAN
Reinforced Masonry Frame 6/30/2023 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 6/30/2023 Approved CAMERON CHABAN
Special/Order Compliance 7/6/2023 Partial Inspection CAMERON CHABAN
Final 2/15/2024 OK to Issue CofO CAMERON CHABAN