523 W 17TH ST 90731

Certificate Information: 523 W 17TH ST 90731

Application / Permit
19016-10000-28356
Plan Check / Job No.
B19LA18933
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan 969 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new moment frame.
Permit Issued
Issued on 7/23/2021
Issuing Office
Current Status
CofC Issued on 1/19/2023

Permit Application Status History

Submitted 9/9/2019 APPLICANT
Assigned to Plan Check Engineer 10/16/2019 DANIEL YIP
Corrections Issued 10/23/2019 DANIEL YIP
Quality Review Completed 10/30/2019 HANS SANTIAGO
Applicant returned to address corrections 11/25/2019 DANIEL YIP
Applicant returned to address corrections 12/16/2019 DANIEL YIP
Plan Check Approved 12/17/2019 DANIEL YIP
Issued 7/23/2021 APPLICANT
OK for CofC 1/12/2023 JOEY BUCHANAN
CofC Issued 1/19/2023 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/10/2019 ELENA LOPEZ
Work Adjacent to Public Way Cleared 12/10/2019 BOK GOH
Housing rent stabilization Cleared 7/1/2021 PHILLIP MUNGUIA

Contact Information

Contractor M A F Construction Inc; Lic. No.: 540983-B 1000 N WESTERN AVENUE STE 201      SAN PEDRO, CA 90732
Engineer Givechi,, Mehrzad; Lic. No.: C45725 344 VIA COLUSA      REDONDO BEACH, CA 90277

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2021 Approved MARK FERRARI
Footing/Foundation/Slab 9/21/2021 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 9/23/2021 Not Ready for Inspection NICK LAROCCA
Deputy Steel/Welding 10/12/2021 Conditional Approval NICK LAROCCA
Footing/Foundation/Slab 11/4/2021 Approved JOEY BUCHANAN
Structural Steel Frame 11/4/2021 Approved JOEY BUCHANAN
Interior/Exterior Lathing 11/29/2021 Approved JOEY BUCHANAN
Final 12/16/2021 Corrections Issued JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 12/16/2021 SGSOV Not Ready JOEY BUCHANAN
Smoke Detectors 12/16/2021 Approved JOEY BUCHANAN
Final 1/12/2023 OK for CofC JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Approved JOEY BUCHANAN