632 N ST ANDREWS PL 90004
Certificate Information: 632 N ST ANDREWS PL 90004
- Application / Permit
- 19016-10000-28355
- Plan Check / Job No.
- B19LA18932
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 4/20/2020
- Issuing Office
- Current Status
- CofC Issued on 10/6/2020
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | MANUEL MONTUFAR |
| Corrections Issued | 10/29/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 11/4/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 12/6/2019 | MANUEL MONTUFAR |
| Plan Check Approved | 2/10/2020 | MANUEL MONTUFAR |
| Issued | 4/20/2020 | APPLICANT |
| OK for CofC | 10/5/2020 | MARK FERRARI |
| CofC Issued | 10/6/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/23/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/28/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| Footing/Foundation/Slab | 6/4/2020 | Conditional Approval | MARK FERRARI |
| Pre-Inspection | 6/4/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 6/4/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 6/4/2020 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 6/10/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Reinf. Concrete | 6/11/2020 | Partial Approval | FELIX CEBALLOS |
| Wood Frame | 7/2/2020 | Corrections Issued | MARK FERRARI |
| Deputy Wood Construction | 7/9/2020 | Partial Approval | FELIX CEBALLOS |
| Reinforced Concrete Frame | 7/16/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 7/16/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/16/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 7/24/2020 | Corrections Issued | MARK FERRARI |
| Final | 8/10/2020 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/10/2020 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 8/10/2020 | Not Ready for Inspection | MARK FERRARI |
| Final | 10/5/2020 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 10/5/2020 | Approved | MARK FERRARI |