10664 N ZELZAH AVE 91344

Certificate Information: 10664 N ZELZAH AVE 91344

Application / Permit
19016-10000-28340
Plan Check / Job No.
B19LA18923
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE A PORTION OF EXISTING RETAIL SPACE TO TEA SHOP W/INDOOR SEATING. REMODEL FOR TEA SHOP, NO ADDITIONAL SQ FT, REMODEL RESTROOM, NEW NON LOAD BEARING WALLS, REMOVE NON LOAD BEARING WALLS, NEW EQUIPMENTS, FIXTURES, FINISHES. NEW BICYCLE PARKING SPACES.
Permit Issued
Issued on 2/23/2021
Issuing Office
Current Status
CofO Issued on 2/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 FARSHAD ALIMOHAMADI
Corrections Issued 10/1/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 10/19/2019 YOUNG KIM
Disabled Access Plans Picked Up 11/4/2019 APPLICANT
Applicant returned to address corrections 7/7/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/13/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/15/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 1/12/2021 FARSHAD ALIMOHAMADI
Issued 2/23/2021 APPLICANT
Building Plans Picked Up 3/1/2021 APPLICANT
CofO in Progress 2/7/2022 JEFFREY FULTON
CofO Issued 2/10/2022 JEFFREY DURAN
Permit Finaled 2/10/2022 JEFFREY DURAN

Permit Application Clearance Information

ZA Case Cleared 1/10/2020 ANNA VIDAL
ZA Case Cleared 2/25/2020 KORA MCNAUGHTON
DAS Clearance Cleared 3/11/2020 SHINE LIN
Eng Process Fee Ord 176,300 Cleared 6/29/2020 GABRIEL ROBLES
Sewer availability Cleared 6/29/2020 GABRIEL ROBLES
Food establishment approval Cleared 1/12/2021 LACDHS APPROVED
Specific Plan Cleared 1/12/2021 WILLIAM CABRERA

Contact Information

Contractor M L C Construction Inc; Lic. No.: 928009-B 17203 E FRANCISQUITO AVE      WEST COVINA, CA 91791

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/22/2021 Corrections Issued JEFFREY FULTON
Wood Frame 6/25/2021 Partial Inspection JEFFREY FULTON
Pre-Inspection 6/29/2021 Partial Inspection JEFFREY FULTON
Wood Frame 6/29/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/15/2021 Approved JEFFREY FULTON
Final 11/23/2021 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Not Required JEFFREY FULTON
Smoke Detectors 11/23/2021 Approved JEFFREY FULTON
Wood Frame 11/23/2021 Approved JEFFREY FULTON
Final 12/7/2021 Not Ready for Inspection JEFFREY FULTON
Final 1/27/2022 OK to Issue CofO JEFFREY FULTON