3726 N LOCKE AVE 90032

Certificate Information: 3726 N LOCKE AVE 90032

Application / Permit
19016-10000-28323
Plan Check / Job No.
B19LA18909
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 2 CANT COLUMNS AND 1 MOMENT FRAME.
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofC Issued on 12/30/2020

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 10/16/2019 DANIEL SANJUAN
Corrections Issued 10/23/2019 DANIEL SANJUAN
Quality Review Completed 10/24/2019 SAI KHUM
Building Plans Picked Up 10/31/2019 APPLICANT
Plan Check Approved 11/15/2019 DANIEL SANJUAN
Issued 9/24/2020 APPLICANT
OK for CofC 12/22/2020 MARK FERRARI
CofC Issued 12/30/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 8/26/2020 STEVEN HOFSTAD

Contact Information

Contractor K N D Construction Inc; Lic. No.: 969756-B 145 S GLENOAKS BLVD #204      BURBANK, CA 91502
Engineer Pachunuri,, Nalin Kumar; Lic. No.: C78970 21126 INGOMAR CT      CANOGA PARK, CA 91304

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/5/2020 Approved MARK FERRARI
Deputy Steel/Welding 10/26/2020 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 10/29/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 10/29/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 10/29/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 10/29/2020 Partial Inspection MARK FERRARI
Wood Frame 10/29/2020 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 11/2/2020 Approved MARK FERRARI
Footing/Foundation/Slab 11/2/2020 Approved MARK FERRARI
Structural Steel Frame 11/2/2020 Approved MARK FERRARI
Wood Frame 11/2/2020 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 11/4/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 11/13/2020 Conditional Approval MARK FERRARI
Deputy Wood Construction 11/13/2020 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Approved MARK FERRARI
Structural Steel Frame 11/18/2020 Approved MARK FERRARI
Wood Frame 11/18/2020 Approved MARK FERRARI
Interior/Exterior Lathing 12/2/2020 Approved MARK FERRARI
Final 12/22/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/22/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 12/22/2020 Approved MARK FERRARI