842 N SYCAMORE AVE 90038
Certificate Information: 842 N SYCAMORE AVE 90038
- Application / Permit
- 19016-10000-28292
- Plan Check / Job No.
- B19LA18882
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY SEISMIC RETROFIT AS PER LABC CH. 93. - INSTALL (N) PLYWOOD SHEAR WALLS AT NORTH AND WEST SIDE OF BUILDING.
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/4/2023
Permit Application Status History
| Submitted | 9/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2019 | DANIEL YIP |
| Corrections Issued | 10/21/2019 | DANIEL YIP |
| Quality Review Completed | 10/30/2019 | SAI KHUM |
| Plan Check Approved | 5/6/2020 | DANIEL YIP |
| Building Plans Picked Up | 5/7/2020 | APPLICANT |
| Issued | 7/18/2022 | APPLICANT |
| OK for CofC | 4/4/2023 | VAHE KELEDJIAN |
| CofC Issued | 4/4/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/15/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Leonel Lemus; Lic. No.: 793263-B | 9446 SOMERSET BLVD BELLFLOWER, CA 90706 |
| Engineer | Marrs,, Nicholas Reidar; Lic. No.: C83398 | 1150 GENEVA ST LIVERMORE, CA 94550 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/19/2022 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Approved | DARRYL ARNOLD |
| Pre-Inspection | 10/28/2022 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 11/1/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 11/16/2022 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 11/30/2022 | Approved | BRUCE CAMPBELL |
| Drywall Nailing | 12/9/2022 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/9/2022 | Approved | DARRYL ARNOLD |
| Final | 12/29/2022 | Corrections Issued | VAHE KELEDJIAN |
| METHANE-Final | 12/29/2022 | Approved | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Gas Company | VAHE KELEDJIAN |
| Smoke Detectors | 12/29/2022 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 3/23/2023 | Partial Inspection | VAHE KELEDJIAN |
| Smoke Detectors | 3/23/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 4/4/2023 | OK for CofC | VAHE KELEDJIAN |
| Smoke Detectors | 4/4/2023 | Approved | VAHE KELEDJIAN |