2349 E SHOREDALE AVE 90031

Certificate Information: 2349 E SHOREDALE AVE 90031

Application / Permit
19016-10000-28124
Plan Check / Job No.
B19LA18786
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) garage to Accessory Dwelling Unit per AB494 and SB229 and add new trellis on new roof deck. New spiral staircase per LA Standard Plan #111.
Permit Issued
Issued on 9/23/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 VU NGUYEN
Corrections Issued 9/5/2019 VU NGUYEN
Plan Check Approved 9/17/2019 KEVIN MORALES
Issued 9/23/2019 LADBS
CofO in Progress 7/26/2021 BRAD BESCOS
Permit Finaled 7/27/2021 DEROLD HAUFF
Permit Finaled 7/27/2021 DEROLD HAUFF
CofO Issued 7/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/5/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/5/2019 JEANETTE VONG
Sewer availability Cleared 9/5/2019 JEANETTE VONG

Contact Information

Contractor Daniel Guerrero Jr; Lic. No.: 911049-B 11148 SEE DRIVE      WHITTIER, CA 90606
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/26/2019 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 12/5/2019 Corrections Issued AJA COLLAY
Footing/Foundation/Slab 12/27/2019 Approved RUBEN SALAS
HVAC-Rough 3/18/2020 Partial Inspection AJA COLLAY
Rough-Elec/Plmb/HVAC 4/20/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/6/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 5/6/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Special/Order Compliance 5/6/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/8/2020 Corrections Issued DAVID CHAN
HVAC-Rough 5/8/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 5/8/2020 Corrections Issued DAVID CHAN
Rough-Elec/Plmb/HVAC 5/8/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 5/27/2020 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 5/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 5/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/27/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/10/2020 Corrections Issued ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 6/10/2020 Partial Approval ROBERT VORHIS
HVAC-Rough 6/10/2020 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 6/10/2020 Corrections Issued ROBERT VORHIS
ELECTRICAL-Rough 7/2/2020 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 7/2/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 7/2/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/14/2020 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 7/14/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 7/14/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/17/2020 Approved STUART CHAPMAN
ELECTRICAL-Rough 8/17/2020 Approved STUART CHAPMAN
Green Building Rough 8/17/2020 Approved STUART CHAPMAN
HVAC-Rough 8/17/2020 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Approved STUART CHAPMAN
Insulation 10/6/2020 Not Ready for Inspection STUART CHAPMAN
Insulation 10/14/2020 Approved STUART CHAPMAN
Drywall Nailing 11/2/2020 Approved STUART CHAPMAN
Shower Pan 11/25/2020 No Access for Inspection STUART CHAPMAN
Shower Pan 12/3/2020 Partial Inspection OSVALDO PARAMO
Shower Pan 2/4/2021 Approved CRAIG VAUGHAN
Gas Test 4/19/2021 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 4/19/2021 Conditional Approval HAMIK HARTOUNIAN
Final 5/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 5/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 5/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 5/21/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 5/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 5/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 6/24/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 6/24/2021 Approved KATHRYN BUTTERWORTH
Smoke Detectors 6/24/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 6/29/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
Smoke Detectors 6/29/2021 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 7/14/2021 Approved SCOTT FINNILA
Final 7/14/2021 Partial Approval SCOTT FINNILA
HVAC-Final 7/14/2021 Approved SCOTT FINNILA
PLUMBING-Final 7/14/2021 Approved SCOTT FINNILA
Final 7/23/2021 OK to Issue CofO BRAD BESCOS