1323 N MICHELTORENA ST 90026

Certificate Information: 1323 N MICHELTORENA ST 90026

Application / Permit
19016-10000-27936
Plan Check / Job No.
B19LA18667
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 3 SCC AND SIMPSON STRONG WALL.
Permit Issued
Issued on 2/12/2020
Issuing Office
Metro
Current Status
CofC Issued on 8/7/2020

Permit Application Status History

Submitted 9/4/2019 APPLICANT
Assigned to Plan Check Engineer 9/25/2019 DANIEL YIP
Corrections Issued 9/30/2019 DANIEL YIP
Quality Review Completed 10/1/2019 HANS SANTIAGO
Building Plans Picked Up 10/8/2019 APPLICANT
Applicant returned to address corrections 10/28/2019 DANIEL YIP
Plan Check Approved 1/15/2020 DANIEL YIP
Issued 2/12/2020 LADBS
OK for CofC 8/6/2020 MARK FERRARI
CofC Issued 8/7/2020 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/1/2019 ELAINE LEI
Work Adjacent to Public Way Cleared 1/15/2020 ARMEN SARKISIAN
Housing rent stabilization Cleared 2/11/2020 ISMAEL HERNANDEZ

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Axsom,, Erich Jason; Lic. No.: S4435 92 CORPORATE PARK C125      IRVINE, CA 92606

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2020 Approved MARK FERRARI
Pre-Inspection 3/26/2020 Approved MARK FERRARI
Deputy Steel/Welding 4/3/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 4/14/2020 Conditional Approval MARK FERRARI
Special/Order Compliance 4/14/2020 Partial Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 4/15/2020 Conditional Approval MARK FERRARI
Special/Order Compliance 4/20/2020 Partial Inspection JOE VELASQUEZ
Wood Frame 4/20/2020 Corrections Issued MARK FERRARI
Wood Frame 4/22/2020 Approved MARK FERRARI
Interior/Exterior Lathing 5/7/2020 Approved FELIX CEBALLOS
Final 5/21/2020 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 5/21/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 5/21/2020 Approved MARK FERRARI
Final 8/6/2020 OK for CofC MARK FERRARI