1566 W 223RD ST 90501

Certificate Information: 1566 W 223RD ST 90501

Application / Permit
19016-10000-27647
Plan Check / Job No.
B19LA18474
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 9/17/2019
Issuing Office
San Pedro
Current Status
CofO Issued on 6/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2019 APPLICANT
Assigned to Plan Check Engineer 9/10/2019 FARSHAD ALIMOHAMADI
Corrections Issued 9/10/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 9/13/2019 SAMUEL GONZALEZ
Issued 9/17/2019 LADBS
CofO in Progress 6/7/2020 JOHN KLARIN
Permit Finaled 6/10/2020 BOB DUNN
CofO Issued 6/10/2020 BOB DUNN
Permit Finaled 6/10/2020 BOB DUNN

Permit Application Clearance Information

Address approval Cleared 9/10/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/10/2019 THOMAS LANG
Sewer availability Cleared 9/10/2019 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/27/2019 No Access for Inspection ANSON MAGLASANG
Pre-Inspection 12/3/2019 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/7/2020 Corrections Issued BOB DUNN
Drywall Nailing 2/7/2020 Not Ready for Inspection BOB DUNN
ELECTRICAL-Rough 2/7/2020 Not Ready for Inspection BOB DUNN
Green Building Rough 2/7/2020 Not Ready for Inspection BOB DUNN
HVAC-Rough 2/7/2020 Not Ready for Inspection BOB DUNN
METHANE-Rough 2/7/2020 Not Ready for Inspection BOB DUNN
Drywall Nailing 2/11/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 2/11/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 2/11/2020 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 2/11/2020 Approved JOHN KLARIN
Shower Pan 2/11/2020 Not Ready for Inspection JOHN KLARIN
Wood Frame 2/11/2020 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 2/13/2020 Conditional Approval JOHN KLARIN
Final 2/13/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 2/13/2020 Not Ready for Inspection JOHN KLARIN
Green Building Rough 2/13/2020 Approved JOHN KLARIN
METHANE-Final 2/13/2020 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 2/13/2020 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/13/2020 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 2/13/2020 Partial Approval JOHN KLARIN
Insulation 2/14/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/20/2020 Approved JOHN KLARIN
Final 2/20/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 2/20/2020 Not Ready for Inspection JOHN KLARIN
METHANE-Final 2/20/2020 Approved JOHN KLARIN
METHANE-Rough 2/20/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/20/2020 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 2/20/2020 Not Ready for Inspection JOHN KLARIN
Final 3/12/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 3/12/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/12/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 3/12/2020 Corrections Issued JOHN KLARIN
Final 4/8/2020 Conditional Approval JOHN KLARIN
Smoke Detectors 4/8/2020 Approved JOHN KLARIN
Final 6/8/2020 OK to Issue CofO JOHN KLARIN