1566 W 223RD ST 90501
Certificate Information: 1566 W 223RD ST 90501
- Application / Permit
- 19016-10000-27647
- Plan Check / Job No.
- B19LA18474
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 9/17/2019
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 6/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/10/2019 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 9/13/2019 | SAMUEL GONZALEZ |
| Issued | 9/17/2019 | LADBS |
| CofO in Progress | 6/7/2020 | JOHN KLARIN |
| Permit Finaled | 6/10/2020 | BOB DUNN |
| CofO Issued | 6/10/2020 | BOB DUNN |
| Permit Finaled | 6/10/2020 | BOB DUNN |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2019 | THOMAS LANG |
| Sewer availability | Cleared | 9/10/2019 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/27/2019 | No Access for Inspection | ANSON MAGLASANG |
| Pre-Inspection | 12/3/2019 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/7/2020 | Corrections Issued | BOB DUNN |
| Drywall Nailing | 2/7/2020 | Not Ready for Inspection | BOB DUNN |
| ELECTRICAL-Rough | 2/7/2020 | Not Ready for Inspection | BOB DUNN |
| Green Building Rough | 2/7/2020 | Not Ready for Inspection | BOB DUNN |
| HVAC-Rough | 2/7/2020 | Not Ready for Inspection | BOB DUNN |
| METHANE-Rough | 2/7/2020 | Not Ready for Inspection | BOB DUNN |
| Drywall Nailing | 2/11/2020 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 2/11/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 2/11/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 2/11/2020 | Approved | JOHN KLARIN |
| Shower Pan | 2/11/2020 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 2/11/2020 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/13/2020 | Conditional Approval | JOHN KLARIN |
| Final | 2/13/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 2/13/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 2/13/2020 | Approved | JOHN KLARIN |
| METHANE-Final | 2/13/2020 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Rough | 2/13/2020 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2020 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 2/13/2020 | Partial Approval | JOHN KLARIN |
| Insulation | 2/14/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/20/2020 | Approved | JOHN KLARIN |
| Final | 2/20/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 2/20/2020 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Final | 2/20/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 2/20/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2020 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 2/20/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 3/12/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 3/12/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2020 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 3/12/2020 | Corrections Issued | JOHN KLARIN |
| Final | 4/8/2020 | Conditional Approval | JOHN KLARIN |
| Smoke Detectors | 4/8/2020 | Approved | JOHN KLARIN |
| Final | 6/8/2020 | OK to Issue CofO | JOHN KLARIN |