1446 S BROCKTON AVE 90025
Certificate Information: 1446 S BROCKTON AVE 90025
- Application / Permit
- 19016-10000-27630
- Plan Check / Job No.
- B19LA18456
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 940 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new moment frame and 2 new SCCS.
- Permit Issued
- Issued on 7/15/2020
- Issuing Office
- Current Status
- CofC Issued on 5/19/2023
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2019 | DANIEL YIP |
| Corrections Issued | 10/16/2019 | DANIEL YIP |
| Quality Review Completed | 10/22/2019 | HANS SANTIAGO |
| Plan Check Approved | 5/14/2020 | DANIEL YIP |
| Issued | 7/15/2020 | APPLICANT |
| OK for CofC | 12/23/2020 | GRANT WOODS |
| CofC Issued | 5/19/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/29/2020 | MICHAEL SOTO |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 8730 COSTA VERDE BLVD APT 2348 SAN DIEGO, CA 92122 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2020 | Not Ready for Inspection | GRANT WOODS |
| Pre-Inspection | 8/12/2020 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 8/27/2020 | Conditional Approval | JOHN DODGE |
| Deputy Steel/Welding | 9/2/2020 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 9/8/2020 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 9/10/2020 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 9/11/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 9/11/2020 | Approved | JOHN DODGE |
| Structural Steel Frame | 9/11/2020 | Approved | JOHN DODGE |
| Wood Frame | 9/11/2020 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 9/15/2020 | Conditional Approval | JOHN DODGE |
| Structural Steel Frame | 10/29/2020 | Approved | JOHN DODGE |
| Wood Frame | 10/29/2020 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 11/13/2020 | Approved | RUSSELL BONVOULOIR |
| Final | 11/20/2020 | Partial Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 11/20/2020 | Approved | GRANT WOODS |
| Final | 12/23/2020 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Approved | GRANT WOODS |