Eplan 940 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new moment frame and 2 new SCCS.
Permit Issued
Issued on 7/15/2020
Issuing Office
Current Status
CofC Issued on 5/19/2023

Permit Application Status History

Submitted 9/3/2019 APPLICANT
Assigned to Plan Check Engineer 10/9/2019 DANIEL YIP
Corrections Issued 10/16/2019 DANIEL YIP
Quality Review Completed 10/22/2019 HANS SANTIAGO
Plan Check Approved 5/14/2020 DANIEL YIP
Issued 7/15/2020 APPLICANT
OK for CofC 12/23/2020 GRANT WOODS
CofC Issued 5/19/2023 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Housing rent stabilization Cleared 6/29/2020 MICHAEL SOTO

Contact Information

Contractor American Retrofitters Corp; Lic. No.: 1020382-B 15643 SHERMAN WAY STE 220      VAN NUYS, CA 91406
Engineer Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 8730 COSTA VERDE BLVD APT 2348      SAN DIEGO, CA 92122

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2020 Not Ready for Inspection GRANT WOODS
Pre-Inspection 8/12/2020 Approved GRANT WOODS
Deputy Steel/Welding 8/27/2020 Conditional Approval JOHN DODGE
Deputy Steel/Welding 9/2/2020 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 9/8/2020 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 9/10/2020 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 9/11/2020 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 9/11/2020 Approved JOHN DODGE
Structural Steel Frame 9/11/2020 Approved JOHN DODGE
Wood Frame 9/11/2020 Conditional Approval JOHN DODGE
Deputy Reinf. Concrete 9/15/2020 Conditional Approval JOHN DODGE
Structural Steel Frame 10/29/2020 Approved JOHN DODGE
Wood Frame 10/29/2020 Approved JOHN DODGE
Interior/Exterior Lathing 11/13/2020 Approved RUSSELL BONVOULOIR
Final 11/20/2020 Partial Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Not Ready GRANT WOODS
Smoke Detectors 11/20/2020 Approved GRANT WOODS
Final 12/23/2020 OK for CofC GRANT WOODS
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Approved GRANT WOODS