18326 W NAPA ST 91325
Certificate Information: 18326 W NAPA ST 91325
- Application / Permit
- 19016-10000-27507
- Plan Check / Job No.
- B19LA18363
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN AND PLYWOOD SHEARWALL.
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/3/2023
Permit Application Status History
| Submitted | 8/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2019 | MANUEL MONTUFAR |
| Corrections Issued | 10/16/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 10/21/2019 | SAI KHUM |
| Building Plans Picked Up | 10/24/2019 | APPLICANT |
| Plan Check Approved | 1/27/2021 | MANUEL MONTUFAR |
| Issued | 3/17/2021 | APPLICANT |
| OK for CofC | 12/9/2022 | KENNETH ROBERTS |
| CofC Issued | 3/3/2023 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/23/2021 | STEVEN HOFSTAD |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | 17321 MURPHY AVENUE #240 IRVINE, CA 92614 |
| Engineer | Bozorgnia,, Behrouz; Lic. No.: C79581 | 1557 WESTWOOD BLVD 145 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 4/12/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 4/13/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 4/16/2021 | Conditional Approval | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 4/22/2021 | Approved | DANIEL VARNUM |
| Wood Frame | 5/6/2021 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 5/14/2021 | Approved | DANIEL VARNUM |
| Final | 7/22/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 7/22/2021 | Approved | KENNETH ROBERTS |
| Final | 8/5/2022 | Corrections Issued | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 8/5/2022 | SGSOV Approved | KENNETH ROBERTS |
| Final | 10/5/2022 | Corrections Issued | KENNETH ROBERTS |
| Final | 12/9/2022 | OK for CofC | KENNETH ROBERTS |