6015 1/2 N FULCHER AVE 91606

Certificate Information: 6015 1/2 N FULCHER AVE 91606

Application / Permit
19016-10000-27332
Plan Check / Job No.
B19LA18240
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 2-CAR GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP. %%%%% see comments %%%%%
Permit Issued
Issued on 2/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/6/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2019 APPLICANT
Assigned to Plan Check Engineer 9/6/2019 FARSHAD ALIMOHAMADI
Corrections Issued 9/6/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 12/5/2019 MICHAEL LOPEZ
No Progress 12/5/2019 KAVIAN REFAHI
Issued 2/5/2020 LADBS
CofO in Progress 8/6/2020 DANIEL ORRANTE
Permit Finaled 8/6/2020 DANIEL ORRANTE
CofO Issued 8/6/2020 DANIEL ORRANTE
Permit Finaled 8/6/2020 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/6/2019 JEANETTE VONG
Sewer availability Cleared 9/6/2019 JEANETTE VONG
Construction near power lines Cleared 11/4/2019 RIDWAN HARDY
Address approval Cleared 12/5/2019 THOMAS LANG

Contact Information

No Data Available.

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/20/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 2/20/2020 Approved RAYMOND KEHOE
ELECTRICAL-Rough 2/24/2020 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 2/24/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 3/4/2020 Corrections Issued RAYMOND KEHOE
Insulation 3/5/2020 Corrections Issued RAYMOND KEHOE
Insulation 3/11/2020 Corrections Issued RAYMOND KEHOE
BUILDING-Rough-Frame 3/16/2020 Approved RAYMOND KEHOE
Insulation 3/16/2020 Approved RAYMOND KEHOE
Drywall Nailing 3/24/2020 Partial Approval MISAEL ESPARZA
Drywall Nailing 3/26/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 4/3/2020 Partial Approval RAYMOND KEHOE
Final 7/6/2020 Corrections Issued RAYMOND KEHOE
Green Building Final 7/6/2020 Approved RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 7/6/2020 SGSOV Approved RAYMOND KEHOE
Smoke Detectors 7/6/2020 Approved RAYMOND KEHOE
ELECTRICAL-Final 7/17/2020 Approved RAYMOND KEHOE
Final 7/17/2020 Not Ready for Inspection RAYMOND KEHOE
HVAC-Final 7/17/2020 Approved RAYMOND KEHOE
PLUMBING-Final 7/17/2020 Approved RAYMOND KEHOE
Final 7/22/2020 Corrections Issued RAYMOND KEHOE
Final 8/6/2020 OK to Issue CofO DANIEL ORRANTE