1241 N TAMARIND AVE 90038

Certificate Information: 1241 N TAMARIND AVE 90038

Application / Permit
19016-10000-27312
Plan Check / Job No.
B19LA18232
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93. (1) CANTILEVERED COLUMN AND (1) ORDINARY MOMENT FRAME
Permit Issued
Issued on 8/20/2020
Issuing Office
Metro
Current Status
Permit Finaled on 1/5/2022

Permit Application Status History

Submitted 8/29/2019 APPLICANT
Assigned to Plan Check Engineer 9/25/2019 VARAND SARKISIAN
Corrections Issued 9/30/2019 VARAND SARKISIAN
Quality Review Completed 10/1/2019 HANS SANTIAGO
Building Plans Picked Up 10/9/2019 APPLICANT
Plan Check Approved 5/22/2020 VARAND SARKISIAN
Issued 8/20/2020 APPLICANT
Permit Finaled 1/4/2022 BRUCE CAMPBELL

Permit Application Clearance Information

Housing rent stabilization Cleared 6/22/2020 ISMAEL HERNANDEZ
Project located in CRA area Cleared 8/13/2020 MICAELA TORRES-GIL

Contact Information

Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2020 Approved FELIX CEBALLOS
Deputy Steel/Welding 4/22/2021 Conditional Approval FRED WOHLFARTH
Deputy Steel/Welding 5/6/2021 Conditional Approval FRED WOHLFARTH
Footing/Foundation/Slab 5/12/2021 Corrections Issued MARK FERRARI
Reinforced Concrete Frame 5/12/2021 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 5/12/2021 Partial Inspection MARK FERRARI
Wood Frame 5/12/2021 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 5/13/2021 Approved MARK FERRARI
Wood Frame 5/13/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 5/18/2021 Approved JONATHAN QUACH
Deputy Reinf. Concrete 5/19/2021 Conditional Approval FRED WOHLFARTH
Interior/Exterior Lathing 5/25/2021 Approved JONATHAN QUACH
Final 6/1/2021 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 6/1/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 6/1/2021 Approved JONATHAN QUACH
Final 6/2/2021 Conditional Approval JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 6/2/2021 Approved JONATHAN QUACH
Final 1/4/2022 Permit Finaled BRUCE CAMPBELL