815 N BENTON WAY 90026
Certificate Information: 815 N BENTON WAY 90026
- Application / Permit
- 19016-10000-27173
- Plan Check / Job No.
- B19LA18141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (N) 3 SCCS.
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- CofC Issued on 8/26/2021
Permit Application Status History
| Submitted | 8/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2019 | VARAND SARKISIAN |
| Corrections Issued | 9/30/2019 | VARAND SARKISIAN |
| Quality Review Completed | 10/7/2019 | SAI KHUM |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Plan Check Approved | 1/31/2020 | VARAND SARKISIAN |
| Issued | 3/15/2021 | APPLICANT |
| OK for CofC | 8/26/2021 | MARK FERRARI |
| CofC Issued | 8/26/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/23/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Seismic Retrofit Solutions Inc; Lic. No.: 1023483-B | 16060 VENTURA BLVD STE 148 ENCINO, CA 91436 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: C84559 | 9163 LEROY STREET SAN GABRIEL, CA 91775 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2021 | Corrections Issued | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 4/14/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Structural Steel Frame | 4/14/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 4/14/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 4/15/2021 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 4/15/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 4/15/2021 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 4/19/2021 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 4/22/2021 | Approved | MARK FERRARI |
| Wood Frame | 4/22/2021 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 4/27/2021 | Conditional Approval | MARK FERRARI |
| Wood Frame | 4/28/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 5/10/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 5/24/2021 | Approved | MARK FERRARI |
| Final | 6/25/2021 | Not Ready for Inspection | MARK FERRARI |
| METHANE-Final | 6/25/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 6/25/2021 | Approved | MARK FERRARI |
| Final | 8/26/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/26/2021 | SGSOV Approved | MARK FERRARI |