3263 N FLETCHER DR 90065

Certificate Information: 3263 N FLETCHER DR 90065

Application / Permit
19016-10000-27149
Plan Check / Job No.
B19LA18114
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FROM SINGLE FAMILY DWELLING TO RESTAURANT. NO EXTERIOR CHANGES. PARKING STRIPING.
Permit Issued
Issued on 5/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 ALBERT SERVIN
Corrections Issued 9/13/2019 ALBERT SERVIN
Quality Review Completed 9/16/2019 GARO TELMI
Building Plans Picked Up 10/21/2019 APPLICANT
Disabled Access Plans Picked Up 10/21/2019 APPLICANT
Applicant returned to address corrections 1/10/2020 ALBERT SERVIN
Plan Check Approved 2/12/2020 ALBERT SERVIN
Issued 5/22/2020 LADBS
CofO in Progress 7/10/2023 RAFAEL CORTES
CofO Issued 7/11/2023 ERNESTO CORRAL
Permit Finaled 7/11/2023 ERNESTO CORRAL

Permit Application Clearance Information

Food Service Establishment Cleared 11/27/2019 KENNETH BROWNE
"Q" conditions Cleared 12/5/2019 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 12/5/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/5/2019 EMIL KYUPELYAN
Supp. Use District POD/CDO/TDO Cleared 12/5/2019 JASON CHAN
DAS Clearance Cleared 2/7/2020 ALBERT SERVIN
Food establishment approval Cleared 2/12/2020 LACDHS APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 4/30/2021 Not Ready for Inspection LANNY MERRICK
Structural Steel Frame 4/30/2021 Corrections Issued LANNY MERRICK
Pre-Inspection 4/7/2022 Corrections Issued MARK FERRARI
Excavation/Setback/Form/Re-Bar 4/28/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 4/28/2022 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 5/2/2022 Partial Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Not Ready for Inspection MARK FERRARI
Interior/Exterior Lathing 6/14/2022 Corrections Issued MARK FERRARI
Insulation 7/25/2022 Partial Approval MARK FERRARI
Insulation 8/2/2022 Approved MARK FERRARI
Drywall Nailing 8/8/2022 Approved MARK FERRARI
Final 5/4/2023 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 5/4/2023 SGSOV Approved RAFAEL CORTES
Smoke Detectors 5/4/2023 Approved RAFAEL CORTES
Wood Frame 5/4/2023 Approved RAFAEL CORTES
Final 6/5/2023 Not Ready for Inspection RAFAEL CORTES
Final 6/8/2023 Partial Approval ALFREDO LOPEZ
Final 7/10/2023 OK to Issue CofO RAFAEL CORTES