5820-5880 E BENNER ST 90042

Certificate Information: 5820-5880 E BENNER ST 90042

Application / Permit
19016-10000-26777
Plan Check / Job No.
B19LA17922
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY FOR RETROFIT AS PER LABC CH. 93 USING 23 STEEL MOMENT FRAMES
Permit Issued
Issued on 2/24/2021
Issuing Office
Current Status
CofC Issued on 2/9/2022

Permit Application Status History

Submitted 8/26/2019 APPLICANT
Assigned to Plan Check Engineer 10/2/2019 DANIEL SANJUAN
Corrections Issued 10/10/2019 DANIEL SANJUAN
Quality Review Completed 10/10/2019 HANS SANTIAGO
Building Plans Picked Up 10/15/2019 APPLICANT
Applicant returned to address corrections 1/13/2021 DANIEL SANJUAN
Plan Check Approved 2/23/2021 DANIEL SANJUAN
Issued 2/24/2021 APPLICANT
OK for CofC 2/8/2022 MARK FERRARI
CofC Issued 2/9/2022 WINSTON DUNNING

Permit Application Clearance Information

HPOZ Cleared 12/18/2020 KATIE DEBIASE
Housing rent stabilization Cleared 2/9/2021 PHILLIP MUNGUIA

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Carpenter,, Lauren D; Lic. No.: S2511 350 S FIGUEROA ST 400      LOS ANGELES, CA 90071

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/9/2021 Approved MARK FERRARI
Footing/Foundation/Slab 5/5/2021 Partial Approval MARK FERRARI
Footing/Foundation/Slab 5/13/2021 Partial Approval MARK FERRARI
Footing/Foundation/Slab 5/20/2021 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 5/21/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 5/24/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 5/25/2021 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 5/26/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 5/27/2021 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 5/27/2021 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 5/28/2021 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 5/28/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 6/1/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 6/1/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 6/2/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 6/2/2021 Conditional Approval MARK FERRARI
Wood Frame 6/2/2021 Partial Inspection MARK FERRARI
Deputy Drilled-In Anchors 6/3/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 6/7/2021 Partial Approval MARK FERRARI
Wood Frame 6/7/2021 Partial Approval MARK FERRARI
Deputy Wood Construction 6/8/2021 Conditional Approval MARK FERRARI
Wood Frame 6/8/2021 Partial Approval MARK FERRARI
Deputy Wood Construction 6/9/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 6/10/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 6/10/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 6/11/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 6/11/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 6/14/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 6/15/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 6/15/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 6/16/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 6/16/2021 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Partial Approval MARK FERRARI
Structural Steel Frame 6/16/2021 Not Ready for Inspection MARK FERRARI
Deputy Wood Construction 6/17/2021 Conditional Approval MARK FERRARI
Structural Steel Frame 6/18/2021 Partial Approval JONATHAN QUACH
Wood Frame 6/18/2021 Corrections Issued JONATHAN QUACH
Deputy Wood Construction 6/21/2021 Conditional Approval MARK FERRARI
Wood Frame 6/21/2021 Partial Inspection MARK FERRARI
Deputy Wood Construction 6/23/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 6/24/2021 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Partial Approval MARK FERRARI
Structural Steel Frame 6/28/2021 Approved MARK FERRARI
Wood Frame 6/28/2021 Partial Approval MARK FERRARI
Wood Frame 6/30/2021 Partial Inspection MARK FERRARI
Drywall Nailing 7/7/2021 Not Ready for Inspection MARK FERRARI
Drywall Nailing 7/13/2021 Partial Approval MARK FERRARI
Drywall Nailing 7/20/2021 Partial Approval MARK FERRARI
Deputy Steel/Welding 7/22/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 7/23/2021 Conditional Approval MARK FERRARI
Structural Steel Frame 7/28/2021 Approved MARK FERRARI
Wood Frame 7/28/2021 Partial Approval MARK FERRARI
Interior/Exterior Lathing 8/16/2021 Partial Approval MARK FERRARI
Deputy Wood Construction 8/17/2021 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Approved MARK FERRARI
Drywall Nailing 8/23/2021 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Not Ready BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Not Ready MARK FERRARI
Final 11/10/2021 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 11/10/2021 Not Ready for Inspection MARK FERRARI
Final 1/3/2022 Not Ready for Inspection MARK FERRARI
Smoke Detectors 1/3/2022 Not Ready for Inspection MARK FERRARI
Final 2/8/2022 OK for CofC MARK FERRARI
Smoke Detectors 2/8/2022 Approved MARK FERRARI