2452 E MALABAR ST 90033
Certificate Information: 2452 E MALABAR ST 90033
- Application / Permit
- 19016-10000-26643
- Plan Check / Job No.
- B19LA17869
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL MOMENT FRAMES
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Metro
- Current Status
- Issued on 8/19/2024
Permit Application Status History
| Submitted | 8/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2019 | MANUEL MONTUFAR |
| Corrections Issued | 9/17/2019 | MANUEL MONTUFAR |
| Re-Submittal Required | 9/17/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 9/27/2019 | APPLICANT |
| Re-Submitted | 10/31/2019 | MANUEL MONTUFAR |
| Corrections Issued 2 | 10/31/2019 | MANUEL MONTUFAR |
| Submitted for Second Quality Review | 10/31/2019 | MANUEL MONTUFAR |
| Plan Check Approved | 12/15/2021 | MANUEL MONTUFAR |
| Issued | 8/19/2024 | APPLICANT |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/13/2024 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 20626 HAYNES ST WINNETKA, CA 91306 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/26/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 1/9/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 1/28/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 1/28/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/4/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/4/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/12/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Not Ready | DARRYL ARNOLD |