10815 W ROSE AVE 90034
Certificate Information: 10815 W ROSE AVE 90034
- Application / Permit
- 19016-10000-26594
- Plan Check / Job No.
- B19LA17848
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL NEW SCCS.
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 6/14/2022
Permit Application Status History
| Submitted | 8/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | DANIEL YIP |
| Corrections Issued | 10/8/2019 | DANIEL YIP |
| Quality Review Completed | 10/16/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 10/18/2019 | APPLICANT |
| Plan Check Approved | 12/12/2019 | DANIEL YIP |
| Issued | 9/10/2020 | APPLICANT |
| OK for CofC | 6/10/2022 | GRANT WOODS |
| CofC Issued | 6/14/2022 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/29/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Classy Builders; Lic. No.: 983036-B | 100 S DOHENY DR #918 LOS ANGELES, CA 90048 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 1836 PARNELL AVE 202 LOS ANGELES, CA 90025 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2021 | No Access for Inspection | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 2/14/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 2/14/2022 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 2/17/2022 | Not Ready for Inspection | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Approved | GRANT WOODS |
| Wood Frame | 3/18/2022 | No Access for Inspection | JOHN DODGE |
| Insulation | 3/30/2022 | Partial Inspection | GRANT WOODS |
| Wall Anchors | 3/30/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 4/7/2022 | Partial Inspection | GRANT WOODS |
| Wood Frame | 5/2/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Steel/Welding | 5/5/2022 | Conditional Approval | PAUL DAVIDSON |
| Insulation | 5/5/2022 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 5/5/2022 | Approved | PAUL DAVIDSON |
| Wood Frame | 5/5/2022 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 5/12/2022 | Conditional Approval | GRANT WOODS |
| Wood Frame | 5/13/2022 | No Access for Inspection | JOHN DODGE |
| Wood Frame | 5/17/2022 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 5/27/2022 | Approved | GRANT WOODS |
| Final | 6/7/2022 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 6/7/2022 | Not Ready for Inspection | GRANT WOODS |
| Final | 6/10/2022 | OK for CofC | GRANT WOODS |
| Smoke Detectors | 6/10/2022 | Approved | GRANT WOODS |