16930 W PARTHENIA ST 91343
Certificate Information: 16930 W PARTHENIA ST 91343
- Application / Permit
- 19016-10000-26513
- Plan Check / Job No.
- B19LA17784
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- CHANGE OF USE FROM (E) RETAIL TO HEALTH CLUB & INTERIOR T.I & INSTALL NON-BEARING PARTITION WALLS.
- Permit Issued
- Issued on 2/2/2021
- Issuing Office
- Current Status
- CofO Issued on 12/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | GARO TELMI |
| Corrections Issued | 9/9/2019 | GARO TELMI |
| Green Plans Picked Up | 9/10/2019 | APPLICANT |
| Quality Review Completed | 9/13/2019 | JOHN FRANCIA |
| Disabled Access Plans Picked Up | 9/27/2019 | APPLICANT |
| Applicant returned to address corrections | 11/13/2019 | GARO TELMI |
| Applicant returned to address corrections | 1/21/2020 | GARO TELMI |
| Applicant returned to address corrections | 11/20/2020 | GARO TELMI |
| Plan Check Approved | 11/25/2020 | GARO TELMI |
| Building Plans Picked Up | 12/22/2020 | APPLICANT |
| Issued | 2/2/2021 | APPLICANT |
| CofO in Progress | 12/10/2021 | ROBERT DAVIS |
| Permit Finaled | 12/14/2021 | JEFFREY DURAN |
| CofO Issued | 12/14/2021 | JEFFREY DURAN |
| Permit Finaled | 12/14/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 9/13/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 9/13/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 9/13/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 9/13/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 9/13/2019 | KIT AWAKUNI |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2019 | ELAINE LEI |
| Sewer availability | Cleared | 9/25/2019 | ELAINE LEI |
| Green Code | Cleared | 12/4/2019 | GARO TELMI |
| DAS Clearance | Cleared | 2/19/2020 | GARO TELMI |
| Fire Marshall Fire Life Safety | Cleared | 2/26/2020 | DOMINIQUE MEDINA |
| ZA Case | Cleared | 9/29/2020 | JASON CHAN |
Contact Information
| Architect | Mullin,, Daniel Kenneth; Lic. No.: C24705 | 517 SOUTH MAIN STREET MOSCOW, ID 83843 |
| Contractor | Rdg Construction Services Inc; Lic. No.: 993728-B | 751 SOUTH WEIR CANYON RD STE 157 ANAHEIM HILLS, CA 92808 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2021 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 8/19/2021 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 8/19/2021 | Approved | JEFFREY FULTON |
| Deputy Reinf. Concrete | 8/20/2021 | Conditional Approval | JEFFREY FULTON |
| Light Gage Steel Frame | 8/25/2021 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 9/15/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 9/15/2021 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 9/23/2021 | Partial Approval | KENNETH ROBERTS |
| Light Gage Steel Frame | 9/29/2021 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 10/1/2021 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 10/1/2021 | Not Ready for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 10/25/2021 | Not Ready for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 10/27/2021 | Corrections Issued | JEFFREY FULTON |
| T-Bar Ceiling | 11/2/2021 | Approved | JEFFREY FULTON |
| Final | 11/10/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 11/10/2021 | Approved | JEFFREY FULTON |
| Green Building Rough | 11/10/2021 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 11/10/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 11/10/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 11/10/2021 | Approved | JEFFREY FULTON |
| Final | 11/12/2021 | OK to Issue CofO | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 11/12/2021 | Approved | ROBERT DAVIS |