4020 N MIDLAND ST 90031
Certificate Information: 4020 N MIDLAND ST 90031
- Application / Permit
- 19016-10000-26453
- Plan Check / Job No.
- B19LA17735
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (1) SPECIAL CANTILEVER COLUMN AND NEW SHEARWALL
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofC Issued on 2/17/2021
Permit Application Status History
| Submitted | 8/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | DANIEL YIP |
| Corrections Issued | 10/8/2019 | DANIEL YIP |
| Quality Review Completed | 10/9/2019 | SAI KHUM |
| Building Plans Picked Up | 10/10/2019 | APPLICANT |
| Plan Check Approved | 10/23/2020 | DANIEL YIP |
| Issued | 11/25/2020 | APPLICANT |
| OK for CofC | 2/16/2021 | MARK FERRARI |
| CofC Issued | 2/17/2021 | TERRY HERR |
Permit Application Clearance Information
| HPOZ | Cleared | 10/22/2020 | KATIE DEBIASE |
| Housing rent stabilization | Cleared | 11/5/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | K N D Construction Inc; Lic. No.: 969756-B | 145 S GLENOAKS BLVD #204 BURBANK, CA 91502 |
| Engineer | Shah,, Satish Sobhagchand; Lic. No.: C56112 | 7611 BLACK STAR LN LA PALMA, CA 90623 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 12/22/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/24/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 12/24/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 12/24/2020 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 12/24/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 12/28/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 12/29/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 1/19/2021 | Not Ready for Inspection | MARK FERRARI |
| Wall Anchors | 1/19/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 1/19/2021 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 1/20/2021 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 1/21/2021 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 1/21/2021 | Conditional Approval | MARK FERRARI |
| Wood Frame | 1/22/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 2/2/2021 | Approved | MARK FERRARI |
| Final | 2/16/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/16/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 2/16/2021 | Approved | MARK FERRARI |