1660 W ANAHEIM ST 90731

Certificate Information: 1660 W ANAHEIM ST 90731

Application / Permit
19016-10000-26378
Plan Check / Job No.
B19LA17682
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
CHANGE OF USE FOR PORTION OF LOCKER SPACE TO GYM. ACCESSORY USE TO MAIN FACILITY ONLY. INTERIOR DEMO OF NON BEARING WALLS, NEW INTERIOR NON BEARING PARTITIONS. NEW CEILINGS AND NEW ACCESSIBLE RESTROOMS, SHOWERS AND ENTRY RAMP.
Permit Issued
Issued on 5/6/2020
Issuing Office
Metro
Current Status
Permit Finaled on 2/2/2021

Permit Application Status History

Submitted 8/22/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 JOE VO
Corrections Issued 9/9/2019 JOE VO
Quality Review Completed 9/16/2019 GARO TELMI
Building Plans Picked Up 9/17/2019 APPLICANT
Disabled Access Plans Picked Up 9/19/2019 APPLICANT
Applicant returned to address corrections 10/15/2019 JOE VO
Plan Check Approved 11/20/2019 JOE VO
Issued 5/6/2020 LADBS
Permit Finaled 2/2/2021 LEOPOLDO MENDOZA

Permit Application Clearance Information

"Q" conditions Cleared 10/1/2019 TERRI OSBORNE
Address approval Cleared 10/1/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/1/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 10/15/2019 ROBERT DUFF
Sewer availability Cleared 10/16/2019 PHILLIP WILSON
DAS Clearance Cleared 11/5/2019 SOMKIAT SUPANYACHOTSKUL
Fire Marshall Fire Life Safety Cleared 11/20/2019 PEJMAN NOORI

Contact Information

Contractor Total-Western Inc; Lic. No.: 506020-A 8049 SOMERSET BLVD      PARAMOUNT, CA 90723

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/8/2020 No Access for Inspection JOEY BUCHANAN
Pre-Inspection 5/11/2020 Approved NICK LAROCCA
Deputy Steel/Welding 6/25/2020 Approved JOEY BUCHANAN
Light Gage Steel Frame 6/30/2020 Not Ready for Inspection JOEY BUCHANAN
Light Gage Steel Frame 8/12/2020 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 9/30/2020 Approved JOEY BUCHANAN
Drywall Nailing 11/9/2020 Approved JOEY BUCHANAN
Final 11/9/2020 No Access for Inspection JOEY BUCHANAN
Light Gage Steel Frame 11/9/2020 Approved JOEY BUCHANAN
METHANE-Final 11/9/2020 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 11/9/2020 Approved JOEY BUCHANAN
Structural Steel Frame 11/9/2020 Approved JOEY BUCHANAN
Final 12/16/2020 No Access for Inspection JOEY BUCHANAN
Final 12/21/2020 Corrections Issued JOEY BUCHANAN
Final 2/2/2021 Permit Finaled LEOPOLDO MENDOZA