1230 N MANSFIELD AVE 90038
Certificate Information: 1230 N MANSFIELD AVE 90038
- Application / Permit
- 19016-10000-26282
- Plan Check / Job No.
- B19LA17613
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (5) STEEL SPECIAL CANTILEVERED COLUMN
- Permit Issued
- Issued on 6/16/2020
- Issuing Office
- Current Status
- CofC Issued on 2/5/2021
Permit Application Status History
| Submitted | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | DANIEL SANJUAN |
| Corrections Issued | 10/9/2019 | DANIEL SANJUAN |
| Quality Review Completed | 10/10/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 10/17/2019 | APPLICANT |
| Applicant returned to address corrections | 1/21/2020 | DANIEL SANJUAN |
| Plan Check Approved | 1/31/2020 | DANIEL SANJUAN |
| Issued | 6/16/2020 | APPLICANT |
| OK for CofC | 2/1/2021 | MARK FERRARI |
| CofC Issued | 2/5/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/27/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Konstruct Inc; Lic. No.: 1037235-B | 3964 BIXBY DR LA VERNE, CA 91750 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/30/2020 | Not Ready for Inspection | EDWIN GREGORYONA |
| Pre-Inspection | 10/26/2020 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/30/2020 | Partial Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 12/11/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 12/11/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 12/16/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 12/22/2020 | Conditional Approval | JONATHAN QUACH |
| Final | 1/25/2021 | Corrections Issued | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/25/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 1/25/2021 | Approved | JONATHAN QUACH |
| Final | 2/1/2021 | OK for CofC | MARK FERRARI |