1129 W 10TH ST 90731
Certificate Information: 1129 W 10TH ST 90731
- Application / Permit
- 19016-10000-26214
- Plan Check / Job No.
- B19LA17564
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETRO FIT AS PER LABC CH 93. INSTALL (1) SCC AND (2) NEW SHEAR WALLS
- Permit Issued
- Issued on 7/8/2020
- Issuing Office
- Current Status
- CofC Issued on 9/23/2020
Permit Application Status History
| Submitted | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | DANIEL SANJUAN |
| Corrections Issued | 10/9/2019 | DANIEL SANJUAN |
| Quality Review Completed | 10/9/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 10/16/2019 | APPLICANT |
| Plan Check Approved | 12/12/2019 | DANIEL SANJUAN |
| Issued | 7/8/2020 | APPLICANT |
| OK for CofC | 9/22/2020 | JOEY BUCHANAN |
| CofC Issued | 9/23/2020 | NICK LAROCCA |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/25/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | N & B Home Improvement / Construction; Lic. No.: 824928-B | 14337 PIONEER BLVD #40 NORWALK, CA 90650 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/22/2020 | Corrections Issued | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 7/27/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 8/7/2020 | Partial Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 8/7/2020 | Partial Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 8/7/2020 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 8/7/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Conditional Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 8/17/2020 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 8/17/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 8/21/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 8/21/2020 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 8/21/2020 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 8/24/2020 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2020 | Partial Approval | JOEY BUCHANAN |
| Interior/Exterior Lathing | 8/27/2020 | Approved | JOEY BUCHANAN |
| Final | 9/22/2020 | OK for CofC | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 9/22/2020 | Approved | JOEY BUCHANAN |