21333 W ERWIN ST 91367
Certificate Information: 21333 W ERWIN ST 91367
- Application / Permit
- 19016-10000-26179
- Plan Check / Job No.
- B19LA17549
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Garage - Public
- Work Description
- NEW SOLAR CANOPY STRUCTURE (16,875SF) ON ROOFTOP OF EXISTING 7-STORY PARKING GARAGE. RESTRIPE TWO EXISTING STANDARD STALLS TO TWO COMPACT STALLS.
- Permit Issued
- Issued on 6/16/2020
- Issuing Office
- Current Status
- CofO Issued on 9/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | CAROLYNN NEPOMUCENO |
| Corrections Issued | 9/23/2019 | CAROLYNN NEPOMUCENO |
| Quality Review Completed | 9/24/2019 | PETER KIM |
| Building Plans Picked Up | 9/25/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 9/25/2019 | APPLICANT |
| Applicant returned to address corrections | 10/17/2019 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 10/30/2019 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 11/8/2019 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 11/20/2019 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 4/23/2020 | KESETE HAREGOT |
| Issued | 6/16/2020 | APPLICANT |
| CofO in Progress | 9/26/2022 | JEFFREY FULTON |
| CofO Issued | 9/26/2022 | JEFFREY DURAN |
| Permit Finaled | 9/26/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 11/7/2019 | SOMKIAT SUPANYACHOTSKUL |
| Specific Plan | Cleared | 12/6/2019 | ALYCIA WITZLING |
| Specific Plan | Cleared | 12/10/2019 | PETE EYRE |
Contact Information
| Contractor | Pcs Gridtech Llc; Lic. No.: 1015744-B | 11661 SAN VICENTE BLVD STE 910 LOS ANGELES, CA 90049 |
| Engineer | Elder,, John Brittan; Lic. No.: S6534 | 5181 S EMERALD PL CHANDLER, AZ 85249 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 6/11/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 6/23/2021 | Conditional Approval | JEFFREY FULTON |
| Masonry Wall/Backfill | 6/23/2021 | Partial Inspection | JEFFREY FULTON |
| Structural Steel Frame | 6/23/2021 | Partial Inspection | JEFFREY FULTON |
| Deputy Steel/Welding | 6/24/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 9/24/2021 | Conditional Approval | JEFFREY FULTON |
| Masonry Wall/Backfill | 9/27/2021 | Approved | DANIEL VARNUM |
| Pre-Inspection | 10/13/2021 | No Access for Inspection | DANIEL VARNUM |
| Final | 5/10/2022 | Partial Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV No Gas | CAMERON CHABAN |
| Smoke Detectors | 5/10/2022 | Approved | CAMERON CHABAN |
| Final | 7/25/2022 | OK to Issue CofO | JEFFREY FULTON |
| Final | 8/15/2022 | Partial Inspection | ALAN NOVAK |