21333 W ERWIN ST 91367

Certificate Information: 21333 W ERWIN ST 91367

Application / Permit
19016-10000-26179
Plan Check / Job No.
B19LA17549
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(8) Garage - Public
Work Description
NEW SOLAR CANOPY STRUCTURE (16,875SF) ON ROOFTOP OF EXISTING 7-STORY PARKING GARAGE. RESTRIPE TWO EXISTING STANDARD STALLS TO TWO COMPACT STALLS.
Permit Issued
Issued on 6/16/2020
Issuing Office
Current Status
CofO Issued on 9/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 CAROLYNN NEPOMUCENO
Corrections Issued 9/23/2019 CAROLYNN NEPOMUCENO
Quality Review Completed 9/24/2019 PETER KIM
Building Plans Picked Up 9/25/2019 APPLICANT
Disabled Access Plans Picked Up 9/25/2019 APPLICANT
Applicant returned to address corrections 10/17/2019 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 10/30/2019 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 11/8/2019 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 11/20/2019 CAROLYNN NEPOMUCENO
Plan Check Approved 4/23/2020 KESETE HAREGOT
Issued 6/16/2020 APPLICANT
CofO in Progress 9/26/2022 JEFFREY FULTON
CofO Issued 9/26/2022 JEFFREY DURAN
Permit Finaled 9/26/2022 JEFFREY DURAN

Permit Application Clearance Information

DAS Clearance Cleared 11/7/2019 SOMKIAT SUPANYACHOTSKUL
Specific Plan Cleared 12/6/2019 ALYCIA WITZLING
Specific Plan Cleared 12/10/2019 PETE EYRE

Contact Information

Contractor Pcs Gridtech Llc; Lic. No.: 1015744-B 11661 SAN VICENTE BLVD STE 910      LOS ANGELES, CA 90049
Engineer Elder,, John Brittan; Lic. No.: S6534 5181 S EMERALD PL      CHANDLER, AZ 85249

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 6/11/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 6/23/2021 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 6/23/2021 Partial Inspection JEFFREY FULTON
Structural Steel Frame 6/23/2021 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 6/24/2021 Conditional Approval ANDREW DORSO
Deputy Drilled-In Anchors 9/24/2021 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 9/27/2021 Approved DANIEL VARNUM
Pre-Inspection 10/13/2021 No Access for Inspection DANIEL VARNUM
Final 5/10/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 5/10/2022 Approved CAMERON CHABAN
Final 7/25/2022 OK to Issue CofO JEFFREY FULTON
Final 8/15/2022 Partial Inspection ALAN NOVAK